-PE-TEMPORARY MODULAR UNIT #2 |
**PRIVATE PROVIDER INSPECTIONS** PACIFICA |
|
|
|
7/12/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
7/11/23 ISSUED LETTER GRANTING AUTHORIZATION FOR |
EARLY START UP TO FIRST INSPECTION PRIOR TO PERMIT |
ISSUANCE. RB |
7/7/23 CONTRACTOR SUBMITTED LETTER REQUESTING |
AUTHORIZATION FOR EARLY START UP TO FIRST |
INSPECTION PRIOR TO PERMIT ISSUANCE. RB |
7/7/23 EMAILED IMPACT OFFICE TO REVIEW. LEM |
6/29/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
6/28/23 - ZONING FAILED. CONTACT PERMIT LIBRIAN TO |
PROCESS. LL |
6/22/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
6/21/23 FILES UPLOADED INCORRECTLY, REJECTED BACK. |
LEM |
6/20/23 PER SHILL, OK TO REJECT PRIOR TO REVIEWS |
BEING COMPLETED, REJECTED BACK. LEM |
6/09/23 RESUB RECEIVED,INCOMING COMPLETE AO |
6/7/23 PER SHILL, OK TO REJECT PRIOR TO REVIEWS |
BEING COMPLETED, REJECTED BACK. LEM |
5/22/23 FEES PAID, PLANS UPLOADED, INCOMING |
COMPLETE. AM |
5/18/23 APPLICANT INVITED TO UPLOAD PLANS AND PAY |