Miscellaneous Information / Notes |
-PE-RENOVATION OF NORTH BUILDING AND NEW CHILLER |
YARD |
**PP INSPECTIONS ONLY** PACIFICA |
|
**PROCESSED IN EPL- NOTIFY SH AT TIME OF |
RESUBMITTAL** |
|
|
7/11/23 ISSUED LETTER GRANTING AUTHORIZATION FOR |
EARLY START UP TO FIRST INSPECTION PRIOR TO PERMIT |
ISSUANCE. RB |
7/7/23 CONTRACTOR SUBMITTED LETTER REQUESTING |
AUTHORIZATION FOR EARLY START UP TO FIRST |
INSPECTION PRIOR TO PERMIT ISSUANCE. RB |
7/7/23 RESUB RECEIVED,INCOMING COMPLETE AO |
7/6/23 TASK SENT BACK PER APPLICANT'S REQUEST, |
NEEDS TO UPLOAD ADDITIONAL DOCUMENTS AO |
6/28/23 NOTIFIED APPLICANT THAT THE RESUBMITTED |
FILES SHOULD INCLUDE ONLY PAGES THAT CHANGED SH |
6/26/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
6/26/23 - ZONING FAILED. CONTACT PERMIT LIBRARIAN |
TO PROCESS. LL |
6/21/23 FILES UPLOADED INCORRECTLY, REJECTED BACK. |
LEM |
6/20/23 PER SHILL, OK TO REJECT PRIOR TO REVIEWS |
BEING COMPLETED, REJECTED BACK. |
6/7/23 PER SHILL, OK TO REJECT PRIOR TO REVIEWS |
BEING COMPLETED, REJECTED BACK. LEM |
5/16/23 APPLICANT INVITED TO PAY FEES AND UPLOAD |
PLANS AO |