Miscellaneous Information / Notes |
GARAGE CONVERSION TO A ROOM |
|
2/24/23 PLANS RELEASED, PERMIT CARD UPLOADED AO |
2/17/23 PLAN REVIEW COMPLETE, WAITING ON EC |
SUB-CONTRACTOR REGISTRATION AO |
2/1/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/25/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
12/19/22 RECEIVED NEW APPLICATION WITH CONTRACTOR, |
WILL NEED A NEW NOC AS WELL. LEM |
11/21/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
10/18/22 PERMIT APPLICATION IS NOT BEING CANCELED. |
RYAN BROWN WENT TO THE PROPERTY AND FOUND THAT |
WORK HAD BEEN DONE WITHOUT PERMIT. RB |
10/17/22 RECEIVED LETTER FROM PROPERTY OWNER |
STATING THAT WORK DID NOT PROCEED AND ASKING FOR |
PERMIT APPLICATION TO BE CANCELED. RB |
10/14/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
9/16/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT SH |
9/2/22 PLANS CORRECTED,INCOMING COMPLETE.CD |
9/1/22 PLANS REJECTED, NEED TO PROPERLY NAME, |
UPLOAD LANDSCAPE ORIENTAIONS AND UPLOAD MISSING |
PLANS.CD |
8/31/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |