Miscellaneous Information / Notes |
INTERIOR RENOVATIONS AS PER PLANS W EXTENSION OF |
ENCLOSED PORCH INTO PRIMARY BEDROOM |
|
|
|
5/16/23 PERMIT ISSUED. LEM |
5/12/23 REVIEWS COMPLETE, WAITING ON FEES TO ISSUE |
PERMIT. LEM |
5/9/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/28/23 RESUBMIT RECEIVED, INCOMING COMPLETE. AM |
4/19/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
04/18/23 RESPONDED EMAILS TO ALBERTO URRECHAGA |
REGARDING BUILDING COMMENTS. JG. |
04/17/23 RESPONDED EMAILS TO ALBERTO URRECHAGA |
REGARDING BUILDING COMMENTS. JG. |
4/17/2023 IMPACT FEE QUEST UPLOADED. PBCGOV |
EMAILED PER JG AO |
4/5/23 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
AM |
03/15/23 MET WITH CESAR PIANTINI TO GO OVER |
COMMENTS. JG. |
3/10/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
03/07/23 ADDED 4X PLAN REVIEW FEE $3775.00. JG. |
2/23/23 RESUB RECEIVED,INCOMING COMPLETE AO |
1/26/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
RESUBMIT AO |
1/13/23 RESUB RECEIVED,PLANS VERSIONED,INCOMING |
COMPLETE AO |
12/20/22 TALKED TO GABRIELE LO FRIA (ENG'R) TO GO |
OVER COMMENTS. JG. |
12/9/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT. CP |
11/13/22 RESUB RECEIVED,PLANS VERSIONED,INCOMING |
COMPLETE AO |
11/6/22 REJECTED TASK BACK TO CUSTOMER, REVISED |
PLANS WERE NOT VERSIONED. EMAILED APPLICANT TO |
REUPLOAD. AO |
10/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
9/22/22 RESUB RECEIVED,PLANS VERSIONED,INCOMING |
COMPLETE AO |
7/28/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
6/6/22 PLANS UPLOADED,INCOMING COMPLETE.CD |
6/3/22 WAITING FOR CORRECTIONS.CD |
5/25/22 PLANS REJECTED, NEED TO ADD SHEET |
DESCRIPTION TO THE MEP PLANS 014 THRU 024. 025 |
CALCS MOVED TO SUPPORTING DOCS.CD |
5/18/22 APPLICANT INVITED TO PAY FEES AND UPLOAD |
PLANS AO |