Miscellaneous Information / Notes |
CHANGE OF USE & OCCUPANCY TO PRIVATE SCHOOL |
|
|
8/12/22 PERMIT ISSUED. LEM |
8/3/22 REVIEWS COMPLETE, WAITING ON IMPACT REVIEW. |
LEM |
8/3/22 RESUB AND FPE LETTER RECEIVED, APPROVED BY |
FIRE W/PROVISO COMMENT. BD |
8/3/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
8/2/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/22/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
VERSIONED,INCOMING COMPLETE AO |
7/21/22 RESUBMITTAL FILES HAD ERROR MESSAGE, |
REJECTED BACK. LEM |
7/12/22 THE BUILDING REVIEW COMMENTS HAVE BEEN |
UPDATED TO CLARIFY SPECIFIC REQUIREMENTS.PV |
7/12/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/7/22 - ZONING PASSED. LL |
6/21/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
3/15/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
3/4/22 - ZONING FAILED. LL |
2/25/22 FAIL FIRE, SEE COMMENTS. BD |
2/22/22 PLANS CORRECTED,INCOMING COMPLETE.CD |
2/8/22 PLANS REJECTED,NEED TO SPARATE AND PROPERLY |
NAME PLAN SHEETS IN THE DRAWING FOLDER.CD |
12/08/21 CONVERTED TO DIGITAL. APPLICANT INVITED |
TO UPLOAD PLANS. AO |
12/8/21 APP ROUTED TO INCOMING PLEASE SEND LINK |
FOR UPLOAD TO CONTRACTOR. TSG |