Miscellaneous Information / Notes |
INSTALLATION OF BOAT DOCK |
|
|
|
2/23/23 PLANS RELEASED. LEM |
12/8/22 PLAN REVIEW COMPLETE, WAITING ON |
CONTRACTOR UPDATE AO |
10/7/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
10/7/22 - ZONING PASSED WITH PROVISO. CONTACT |
PERMIT LIBRARIAN TO PROCESS OUT. LL |
9/23/22 RESUB RECEIVED, INCOMING COMPLETE AO |
7/26/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/25/22 - ZONING FAILED. LL |
7/12/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
VERSIONED,ORIENTATION NOT CORRECTED TO MATCH |
ORIGINAL FILE,INCOMING COMPLETE AO |
6/21/22 CUSTOMER ONLY UPLOADED ONE FILE, REJECTED |
BACK TO ADDRESS ALL REVIEW COMMENTS. LEM |
12/30/21 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT. CP |
12/30/21 - ZONING FAILED. CONTACT PERMIT LIBRARIAN |
TO PROCESS. LL |
12/28/21 REMOVED EXPEDITED REQUEST AND FEES SH |
12/17/21 ADDED EXP FEES. CT |
12/17/21 PLANS UPLOADED,INCOMING COMPLETE.CD |
12/2/21 RECEIVED EXPEDITE REQUEST. LEM |
12/2/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |