Miscellaneous Information / Notes |
NEW CONSTRUCTION - TACO BELL |
|
|
|
|
2/22/23 CO ISSUED AND EMAILED TO ADAM HODES. |
SCANNING FOR FILENET. ATTACHED IN C+. FILED UNDER |
THE LETTER "I" SD |
1/5/23 TCO EXTENSION REQUESTED. FEE ADDED AND |
PAID. TCO2 ISSUED AND EMAILED TO KRYSTYAL PERDOMO |
. KP |
10/11/22 ENGINEERING VN HAS VERIFIED THAT |
ENGINEERING IS COMPLETE, SO THE TCO HAS BEEN |
ISSUED. DB |
9/22/22 LANDSCAPE INSP GOOD FOR TCO FOR BUILDING |
B.SA |
4/18/22 PERMIT ISSUED. LEM |
4/13/22 TASK COMPLETED, NOTHING UPLOADED, NEEDS TO |
RESUBMIT FOR IMPACT. LEM |
4/10/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
4/4/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
COMPLETE AO |
3/29/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
3/3/22 APPLICANT RESUBMITTED DIGITALLY,INCOMING |
COMPLETE AO |
2/25/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/18/22 RESUB PASS FIRE BD |
1/13/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/6/22 TASK COMPLETED, CUSTOMER REQUESTED TO ADD |
FILES, REJECTED BACK. LEM |
12/8/21 REVIEWS COMPLETE, APPLICATN NEEDS TO |
RESUBMIT. LEM |
11/17/21 RESUBMITTAL PASS FIRE JC |
11/4/21 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
11/3/21 TASK COMPLETE, WAITING ON EMAIL FROM |
CUSTOMER TO PROCESS RESUBMITTAL, QUITE A FEW NEW |
SHEETS SHOWED NO CHANGES TO ORIGINALS IN SYSTEM. |
LEM |
9/8/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
7/23/21 PASS BY FIRE. BD |
7/19/21 PLANS CORRECTED,INCOMING COMPLETE.CD |
7/15/21 PLANS REJECTED, NEED TO SEPARATE AND |
PROPERLY NAME THE 61 SHEET PLANS. CUSTOMER EMAILED |
TO CORRECT.CD |
07/14/2021 CHK RECIEVED, COPY OF RECEIPT IS |
ATTACHED LF. |
6/30/21 APPLICANT INVITED TO UPLOAD PLANS OR |
DOCUMENTS AND PAY FEES. CC |