Miscellaneous Information / Notes |
NEW CONTRUCTION OF 2-STORY BUILDING |
|
|
|
|
|
5/1/2023 TCO FEE PAID. TCO ISSUED AND EMAILED TO |
LUIS VALENCIA. SCANNING FOR FILENET. ATTACHMENT IN |
C+. FILED UNDER "A". JPB |
4/28/23 CO REVIEW DEFICIENT-NEEDED 402 GAS FINAL |
FOR GAS PERMIT AND A SITE PLAN AMENDMENT TO KEVIE |
DEFRANC JPB |
12/13/21 UPLOADED MECH SUB INTO PROJECTDOX. PAPER |
ROUTED TO DECEMBER STORAGE BOX IN SCANNING.CD |
12/10/21 REVIEWS COMPLETE, WAITING ON FEES TO |
ISSUE PERMIT. LEM |
12/2/21 REVIEWS COMPLETE, WAITING ON IMPACT. LEM |
11/17/21 PASSED BY FIRE.PML |
11/16/21 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
COMPLETE AO |
11/12/2021 SURVEY DRAWING WAS A SIGNED AND SEALED |
ORIGINAL PAPER DRAWING. ME |
11/12/21 INCOMING COMPLETE. PAPER ROUTED TO |
MEDWARDS FOR SIGNATURE REVIEW.CD |
11/12/21 PLANS DROPPED OFF FOR SIGNATURE REVIEW, |
ROUTED TO INCOMING. AM |
*11/05/21 PLAN REVIEW COMPLETE, APPLICANT INVITED |
TO RESUBMIT. CC |
10/28/21 CHANGED INCOMING DATE FROM 10/13 TO 10/6 |
(SUBMITTED 10/6, NEEDED TO RENAME FOR RESUBMITTAL) |
SH |
10/15/21 PASSED BY FIRE.PML |
10/13/21 PLANS UPLOADED, INCOMING COMPLETE. LEM |
10/13/21 FIXED NAMING OF FILES, ADDED ADMIN FEE |
PER SH. LEM |
10/2/21 FILES ARE NOT IN ORDER, EMAILED APPLICANT |
SH |
09/23/21 PLAN REVIEW COMPLETE, APPLICANT INVITED |
TO RESUBMIT CC |
8/16/21 FAILED BY FIRE WITH COMMENTS.PML |
8/13/21 CUSTOMER RESUBMITTED DIGITALLY, INCOMING |
COMPLETE AO |
7/15/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
6/16/21 FAILED BY FIRE WITH COMMENTS.PML |
5/28/21 PLANS CORRECTED,INCOMING COMPLETE.CD |
5/27/21 REJECTED PLANS, EMAILED CUSTOMER TO |
CORRECT.CD |
5/21/21 APPLICANT INVITED TO PAY FEES AND UPLOAD |
PLANS. AO |