Miscellaneous Information / Notes |
NEW CONSTRUCTION OF SINGLE STORY SINGLE FAMILY |
HOUSE |
|
3/8/23 DOCUMENTS ARE READY FOR PICK UP (B FILE) CM |
|
1/19/23 RENEWED PERMIT TO JULY 21, 2023 JPB |
2/26/21 MARK PICKED UP PERMIT. AM |
1/13/2021 THE MISSING PLAN PAGES HAVE BEEN ADDED |
TO TO (PAPER) PLAN SETS.PV |
1/13/21 UPDATED PAPER PAGES BROUGHT IN PLACED ON |
PETER DESK. TSG |
8/11/2020 PLANS PLACED ON THE DESK OF PETER |
VALENTI, WAITING ON UPDATED PAPER PAGES FROM |
ENGINEER.PV |
8/11/2020 BUILDING REVIEW APPROVED.PV |
8/5/2020 ZONING COMPLETED THEIR 2ND REVIEW. PLANS |
PLACED IN PERMIT LIBRARY OUT BOX.PV |
7/29/2020 PLANS ROUTED TO ZONING BIN.PV |
7/29/2020 BUILDING REVIEW FAILED.PV |
7/29/2020 ROOFING AND MECHANICAL REVIEWS |
APPROVED.PV |
7/18/2020 SUBMITTED VIA DROP BOX; ROUTED TO PLAN |
REVIEW RES |
03/10/20 APPLICATION DENIED, EMAILED APPLICANT, |
FILED LARGE DENIED BIN "M"LEM |
02/28/20 APPROVED BY PLUMBING AND PUT BACK IN R13, |
LAC |
2/25/2020 BUILDING, ROOFING, MECHANICAL |
FAILED.RETURNED PERMIT PACKAGE TO BIN R-13.PV |