Miscellaneous Information / Notes |
RENOVATE OFFICE AS PER PLANS |
|
|
6/22/20 PG EMAILED CO TO KURT & KEVIN. ORIGINAL |
UNDER "S". ATTACHED IN C+. GAVE TO SCANNING FOR |
FILENET. |
5/9/2020 SOME PLANS AND A RESUBMITTAL REVISION |
FORM WAS LEFT IN DROP BOX; EMAILED APPLICANT FOR |
CLARIFICATION ON HOW TO PROCESS; ON RACHEL'S DESK |
RES |
02/03/2020 ** APPROVED, PENDING FEES ** CUSTOMER |
INFORMED, PERMIT READY FOR ISSUANCE. FILED IN |
LARGE "A". CC |
1/31/20 KEVIN RESUB TO ADDRESS DENIED COMMENTS BB |
01/24/2020 APPLICATION DENIED, EMAILED APPLICANT, |
FILED LARGE DENIED BIN "A" SPALMER |
1/23/20 PASSED BY FIRE RETURNED TO C08.PML |
1/17/20 - ZONING APPROVED W PROVISOS. SENT TO CSD |
LIBRARY FOR ROUTING. LL |
1/15/20 KEVIN RESUB TO ADDRESS DENIED COMMENTS SL |
1/2/20 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"A". CP |
1/2/20 - ZONING FAILED. SENT TO CSD LIBRARY FOR |
PROCESSING. LL |
12/31/19 ADDED 4X FEE BASED ON CONTRACTOR PROVIDED |
VALUE, SENT EMAIL TO ACLANGE TO CONFIRM SH |
12/30/19 RECEIVED EXPEDITED PLAN REVIEW REQUEST, |
FORWARDED TO FILENET SH |
12/23/19 CUSTOMER RESUB TO ADDRESS DENIED COMMENTS |
BB |
12/4/19 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"A". CP |
11/25- MECH FAILED/RETURNED TO C13/CC |
11/13/2019 PULLED OUT ROOFING AND SKYLIGHTS |
PORTION OF THIS MASTER PERMIT AND CREATED SEPARATE |
PERMITS RES |
11/5/19 - ZONING FAILED. SENT TO CSD LIBRARY FOR |
ROUTING. LL |
10/31/19 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
C13.PML |