Miscellaneous Information / Notes |
NEW TENANT IMPROVEMENTS BUILDOUT **SEE PLUMBING |
REVIEW, REVISION REQUIRED PRIOR TO 1ST |
INSPECTION** |
|
|
|
|
|
7/17/19 PETER P/UP PERMIT SHOLDER |
7/16/19 MOVED PLANS TO LARGE "TBD3". AM |
7/15/19 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
READY TO BE PICKED UP, FILED UNDER SMALL "TBD". CP |
7/11/19 PLUMBING APPROVED WITH PROVIS RETURN TO |
B27/GPJ |
7/8/19 PASSED BY FIRE RETURNED TO B27.PML |
7/9/19 PLB AND GREASE COMPLETED. ROUTED TO B27.TLH |
6/20/19 KYLE RESUB TO ADDRESS DENIED COMMENTS. AM |
6/13/19 APPLICATION DENIED, EMAILED APPLICANT, |
FILED SMALL DENIED BIN "TBD"LEM |
06/13/19 TALKED TO AMMY TO GO OVER COMMENTS. JG. |
6/12/19 PLUMB DENIED SENT TO ZONINGS BOX/GPJ |
06/11/19 TALKED TO KARL TO GO OVER COMMENTS. JG. |
5/23/19 PASSED BY FIRE WITH PROVISO COMMENTS, |
RETURNED TO B14.PML |
5/21/19 KYLE RESUB TO ADDRESS DENIED COMMENTS. AM |
5/9/19 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
"TBD". CP |
5/1/19 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
B25.PML |