Miscellaneous Information / Notes |
FOUNDATION WORK UP TO CONCRETE SLAB FOR APARTMENT |
BUILDING (BLDG PERMIT 19030235) |
|
|
7/17/2020 RECEIVED NOC RES |
05/01/20 RECIEVED ENGINERING LETTER, ROUTED TO KEN |
CONRAD LF. |
9/18/2019 PICK UP PERMIT CARD ONLY RES |
9/17/19 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS & PICK UP PERMIT CARD. CP |
9/17/19 PERMIT ISSUED; CARD AT FRONT COUNTER 'V' |
SH |
9/13/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
9/12/19 ORIGINAL APPLICATION TURNED IN TODAY |
SPALMER |
9/11/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
8/28/19 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
8/27/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
8/16/19 RESUBMIT REMINDER SENT. LEM |
7/17/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
6/5/19 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
5/29/19 CONTRACTOR INCLUDED VERTICAL CONCRETE IN |
VALUE; CHANGED FROM $8M TO $1,187,113 AND ADDED |
$6,812,887 TO BUILDING PERMIT 19030235 SH |
5/29/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
5/28/19 WAITING ON APPLICANT TO GIVE CORRECTED |
SHEET PAGE 087. LEM |
5/15/19 RESUBMIT REMINDER SENT. LEM |
4/15/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
3/22/19 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
PLAN REVIEW.PML |
3/7/19 FEES PAID, INCOMING COMPLETE. LEM |
3/6/19 PLANS UPLOADED, WAITING ON FEES. LEM |
3/6/19 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |