Miscellaneous Information / Notes |
DREYFOOS LOBBY EXPANSION BUILDING |
**PRIVATE PROVIDER** |
|
******ZONING PROVISOS APPLY****** |
|
|
12/28/20 CC EMAILED TO [email protected], |
[email protected] AND [email protected]. |
SCANNING FOR FILENET. ATTACHEMENT IN C+. FILED |
UNDER "W". KP |
4/29/20 EXTENDED TCO TO 7/29/20. (SEE NOTES) SAK |
2/4/20 EXTENDED TCO TO 4/29/20. SAK |
10/29/19 ISSUED TCO. SAK |
10/25/19 RECEIVED TCO REQUEST. SAK |
3/20/19 PLANS IN FILENET. LEM |
2/22/19 PENNY P/U PERMIT SPALMER |
2/21/19 REVIEWS COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, NEEDS TO SUBMIT ORIGINAL |
APPLICATION, NEEDS TO PAY FEES, NEEDS TO PICK UP |
PERMIT CARD. LEM |
2/14/19 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/31/19 REVIEWS COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/22/19 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
CP |
1/11/19 ISSUED LETTER AUTHORIZING EARLY START UP |
TO FIRST INSPECTION. RB |
1/6/18 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. CP |
1/4/19 PASSED BY FIRE WITH PROVISO COMMENTS IN |
DIGITAL PLAN REVIEW.PML |
12/21/18 ADJUSTED FEES TO ACCOMODATE ROOFING |
PERMIT 18120784. LEM |
12/12/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
12/6/18 RESUBMIT REMINDER SENT. LEM |
11/6/18 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. CP |
10/15/18 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
9/26/18 FEES PAID, INCOMING COMPLETE. LEM |
9/26/18 FEES PAID, WAITING ON CORRECTED PAGES |
BEFORE REVIEW. LEM |
9/25/18 PLANS UPLOADED, WAITING ON FEES. LEM |
9/21/18 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |