Miscellaneous Information / Notes |
MASTER 18040936 PLUMBING SUB FOR MASTER 18040936 |
|
|
4/12/23 ABANDONED PERMIT EXPIRED FOR CLEAN UP.CD |
|
4/26/18 THIS SHOULD HAVE BEEN A RESUB WITH AN |
APPLICATION FROM A GC, BUT A NEW APPLICATION WAS |
GENERATED. THEREFORE, THIS IS NOW A SUB PERMIT TO |
MASTER 18040936. OLD PLANS AND APPLICATION WERE |
PUT WITH THE NEW APPLICATION SH |
|
4/19/18 SEE NOTES NATALEE |
3/20/18 TASKIN SIGNED OUT 1 SET OF PLANS SHOLDER |
3/20/18 RETURNED SUBMITTAL TO APPLICANT AS |
BUILDING,IMPACT AND MECHANICAL COMMENTS WERE NOT |
ADDRESSED. APPLICANT CAME IN TO THE OFFICE TO |
REQUEST THAT A PLUMBING PERMIT BE ISSUED AS |
PLUMBING REVIEW HAS PASSED. SINCE THE ISSUE OF WHO |
IS ACTING AS PRIME CONTRACTOR HAS NOT BEEN |
RESOLVED, AND IMPACT FEE ASSESSMENT HAS NOT BEEN |
DONE, AND PLUMBING INFORMATION IS ON ALL THREE OF |
THE PAGES, ISSUANCE OF A PLUMBING PERMIT IS NOT |
POSSIBLE AT THIS TIME. I RETURNED THE SUBMITTAL |
(RESUB FORM, ELECTRICAL SHEETS) TO APPLICANT AND |
INSTRUCTED FOR HIM TO CHECK OUT ONE SET OF PLANS |
TO TAKE TO IMPACT FEE, GAVE HIM THE ADDRESS AND |
WROTE INSTRUCTIONS. ALSO TOLD HIM THAT IT IS |
POSSIBLE THAT THE PLUMBING CONTRACTOR CAN BE THE |
PRIME CONTRACTOR, INSTRUCTED FOR HIM TO HAVE THE |
PLUMBER (QUALIFIER) CALL ME TO DISCUSS. SH |
3/19/18 TASKIN RESUB PER DENIED COMMENTS RES |
3/15/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
"A". CP |
3/13/18 PLUMB APPROVED SENT TO SH BY GPJ |
2/28/18 PASSED BY FIRE RETURNED TO C15.PML |
2/21/18 TASKIN RESUB TO ADDRESS DENIED COMMENTS SL |
2/2/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
"A". CP |
1/11/18 PASSED BY FIRE RETURNED TO C11.PML |
1/10/18 ADDITIONAL PERMITS MAY BE REQUIRED; THIS |
SHOULD BE DETERMINED PRIOR TO ISSUANCE (PRINT HOLD |
ADDED) SH |
1/9/18 PER SHILL, PERMIT SHOULD BE A CHANGE OF |
OCCUPANCY. LEM |
01/02/2018 TASKIN RESUB TO ADDRESS DENIED COMMENTS |
JS |
12/19/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
"A". CP |
12/19/17 - DENIED/SENT TO INCOMING. TKL. |