Miscellaneous Information / Notes |
FOUNDATION FOR NEW CONDO BUILDING "THRESHOLD BLDG" |
|
"ELEVATION CERTIFICATE REQUIRED" |
|
|
|
4/11/19 PERMIT REOPENED. UNKNOWN WHY IT WAS |
CLAOSED. DH |
12/12/18 COURTNEY PICKED UP PERMIT BB |
12/10/18 READY FOR ISSUANCE UPON SUBMITTAL OF |
IMPACT FEE RECEIPT AND STAMPED PLANS, AND PAYMENT |
OF PERMIT FEES, PLANS IN LARGE DENIED ?A?. CP |
12/05/2018 - ZONING APPROVED. SENT TO CSD LIBRARY |
FOR ROUTING. LL |
11/29/18 RESUB ADDRESSING DENIED COMMENTS NO FEE |
SPALMER |
11/27/18 BRIAN SIGNED OUT 1 SET OF PLANS SPALMER |
11/14/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"A". CP |
11/7/18 PLANS RESUBMITTED AND SENT TO ROUTING/CC |
10/26/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"A". CP |
10/24/18 - ZONING PASSED. SENT TO CSD LIBRARY FOR |
ROUTING. LL |
10/17/18 BRIAN RESUB TO ADDRESS DENIED COMMENTS BB |
10/9/18 BRIAN SIGNED OUT 1 SET OF PLANS SL |
6/4/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
"A". CP |
6/4/18 DENIED SENT TO LIB BY GPJ |
5/31/18 - ZONING FAILED. RETURNED TO C2. LL |
04/30/18 RESUB ADDRESSING DENIED COMMENTS BB |
4/23/18 CODY SIGNED OUT 1 SET OF PLANS SPALMER |
4/19/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED "IN DRAW MARKED |
17111142". CP |
4/18/18 - ZONING FAILED. SENT TO SHILL FOR |
BUILDING REVIEW PER REQUEST. LL |
4/10/18 PLUMBING DENIED RETURN TO C02/GPJ |
3/23/18 BUILDING REVIEWED AND RETURNED TO C02. AL |
3/21/18 TRISTA RESUB TO ADDRESS DENIED COMMENTS SL |
12/29/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED "ABOVE FILING |
CABINET". CP |
12/29/17 - ZONING FAILED. SENT TO CSD LIBRARY FOR |
PROCESSING. LL |
12/20/17 PLUMB DENIED SENT TO ZONING BY GPJ |
12/7/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
C02.PML |
12/5/17 BUILDING REVIEWED AND RETURNED TO C02. AL |