Miscellaneous Information / Notes |
INTERIOR BUILDOUT OF NEW DENTAL IMPLANT FACILITY |
|
|
|
|
|
|
12/20/2018 CERTIFICATE OF COMPLETION PRINTED AND |
PLACED AT FRONT COUNTER, FILED UNDER H WITH COPY |
SENT TO SCANNING. COPY OF CERTIFICATE ALSO |
ATTACHED TO THIS PERMIT. MM |
4/10/18 KEVIN P/U TCO SPALMER |
4/10/18 TCO PRINTED, FEES ADDED. IN CO BOX UNDER H |
DH |
4/5/18 STILL NO FINAL INSPECTION REQUESTS FOR |
STOCKING IN THE SYSTEM. CALLED LAUREN AND ADVISED. |
SHE STATED THE SUPERINTENDENT WAS PLANNING TO CALL |
FOR INSPECTIONS AND SHE WOULD FOLLOW UP WITH HIM. |
DH |
3/27/18 REQUEST FOR TCO ROUTED TO DOUG HARVEY |
SPALEMR |
2/9/18 LAUREN P/U PERMIT SPALMER |
2/9/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
READY TO BE PICKED UP, FILED UNDER LARGE "TBD". CP |
1/24/18 PASSED BY FIRE WITH PROVISO COMMENTS, |
RETURNED TO C25.PML |
1/23/18 PLUMB APPROVED RETURN TO C25/GPJ |
1/18/18 LAUREN RESUB TO ADDRESS DENIED COMMENTS |
SHOLDER |
1/5/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"TBD3". CP |
1/5/18 DENIED SENT TO LIB BY GPJ |
12/1/17 ASHLEY RESUB TO ADDRESS DENIED COMMENTS |
11/8/17 PLANS IN LARGE DENIED TBD3 / CC |
10/18/17 TABITHA P/U 1 SET OF PLANS NATALEE |
10/18/17 - DENIED/CONTACTED CONTR./PLACED IN LARGE |
DENIED UNDER "TBD-3.TKL. |
9/14/17 MECH FAILED/RETURNED TO C17/CC |