Miscellaneous Information / Notes |
COMMERCIAL RENOVATION CHANGE OF USE FROM "B" TO |
"I2" |
|
2/17/23 ABANDONED PEMIT EXPIRED. LAST INSPECTION |
DONE ON 5/14/21.CD |
|
CBAA DOCS ATTACHED - JULY 15 2021 HEARING - - - > |
> > |
CBAA DOCS ATTACHED - JUNE 17 2021 HEARING - - - > |
> > |
|
3/18/21 PLANS READY (C FILE)CM |
|
4/7/20 ISSUED TCO. ORIGINAL IN BOX, EMAILED COPY |
TO STAKEHOLDERS AND FILENET. SAK |
4/6/20 AWAITING COMFIRMATION FROM FIRE FOR TCO |
ISSUANCE. SAK |
3/25/20 TCO REQUEST ATTACHED DATED 9/19/19. |
PROVIDED ANALYSIS TO MIGUEL, SEE NOTES. SAK |
3/1/18 MIGUEL AND AMNON PICKED UP PERMIT RES |
3/1/18 PLAN SETS SEPARATED & GIVEN TO RES FOR |
ISSUANCE TO WAITING CUSTOMER. SAK |
2/21/18 MIGUEL CHECKED OUT 1 SET OF PLANS FOR |
IMPACT NATALEE |
2/14/18 APPLICATION DENIED, EMAILED APPLICANT, |
FILED LARGE DENIED BIN "D"LEM |
2/13/18 - ZONING APPROVED W PROVISO. SENT TO CSD |
LIBRARY FOR PROCESSING. LL |
2/12/18 GIVEN TO LLOUIE. LEM |
2/9/18 PASSED BY FIRE RETURNED TO C05.PML |
02/05/18 DAVID RESUB TO ADDRESS DENIED COMMENTS BB |
2/1/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"D". CP |
1/31/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"D". CP |
1/30/18 - ZONING FAILED. SENT TO CSD LIBRARY FOR |
PROCESSING. LL |
1/25/18 PASSED BY FIRE RETURNED TO C05.PML |
1/22/18 RESUB TO ADDRESS DENIED COMMENTS SL |
1/22/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"D". CP |
1/19/18 PASSED BY FIRE, FORWARDED TO PROCESSING |
OUT BOX.PML |
1/18/18 PLUMB APPROVED PLACED IN FIRE BIN BY GPJ |
1/9/18 - ZONING FAILED. RETURNED TO C5. LL |
12/21/17 DAVID RESUB TO ADDRESS DENIED COMMENTS BB |
11/2/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
"D". CP |
10/27/17 FIRE HAS NOT RECEIVED THE APPLICABLE 61G |
DOCUMENTS AND HAS RECEIVED NO CONTACT FROM |
APPLICANT. FAILED BY, PLANS IN C05.PML |
10/23/17 - ZONING FAILED. RETURNED TO BOX C5. LL |
10/19/17 FIRE CONTACTED MIQUEL REFERENCE NO 61G |
SPRINKLER DOCUMENTS. HE WILL TRY TO GET THEM TO ME |
IN A WEEK, FIRE WAITING FOR THOSE DOCUMENTS BEFORE |
PASSING.PML |
10/17/1/ MIGUEL RESUB TO ADDRESS DENIED COMMENTS |
SHOLDER |
8/10/17 IN LARGE DENIED D CONT CUST/GPJ |
8/9/17 REMOVED FROM THE BOARD, GIVEN TO GJOHNSON. |
LEM |
7/26/17 - ZONING FAILED. RETURNED TO C11. LL |
7/19/17 PLUMB DENIED RETURN TO C11/GPJ |
7/18/17 ELEC DENIED, RETURN TO C11. JP |
|
7/13/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
C11.PML |