Miscellaneous Information / Notes |
INTERIOR RENOVATION, CHANGE OF OCCUPANCY FROM A2 |
TO A3, MEP WORK, NFIP SUB.IMP:**ELEVATION |
CERTIFICATE REQUIRED** |
|
|
|
|
|
10/19/17 CHANGE OF CONTRACTOR $100 SPALMER |
3/8/17 BRETT PICKED UP PERMIT RES |
2/28/17 READY IN LARGE B/CALLED CONTR/CC |
2/24/17 JEFF RESUB PER DENIED COMMENTS MECHANCIAL |
RES |
2/23/17 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
RESUBMIT, FILED UNDER SMALL LARGE "B". CP |
2/14/17 PACKAGE AND PLANS IS AT MY DESK SHOLDER |
***NFIP SUBSTANTIAL IMPROVEMENT; ELEVATION |
CERTIFICATE RECEIVED VIA EMAIL, AN UPDATED EC WILL |
BE REQUIRED PRIOR TO FINAL INSPECTION (DFE IS |
16.5, EXISTING FFE IS 18.13)**** SH |
2/10/17 PLUMB APPROVED RETURN TO B36/GPJ |
2/7/17 RESUB ADDRESSING DENIED COMMENTS NO FEES GD |
1/25/17 APPLICATION DENIED, EMAILED APPLICANT, |
FILED LARGE DENIED BIN "B"LEM |
1/23/17 PLUMB DENIED RETURN TO B39/ GPJ |
1/19/17 PASSED BY FIRE, RETURNED TO B39.PML |
1/9/17 CONFIRMED W/ACL THAT VALUE OF WORK DONE |
WITHOUT PERMIT IS OK FOR PURPOSE OF PENALTY |
ASSESSMENT, ADJUSTED VALUE PER CONTRACTOR SUPPLIED |
VALUE VIA EMAIL SH |
12/22/16 RESUB ADDRESSING DENIED COMMENTS NO FEE |
SPALMER |
11/28/16 IN ALRGE DENIED D CONT CUST /GPJ |
11/04/16 RESUB ADDRESSING DENIED COMMENTS NO FEE |
SPALMER |
8/6/16 - DENIED/CONTACTED CONTR./PLACED IN LARGE |
DENIED UNDER "B".TKL. |
7/18/16 REQUEST FOR EXPEDITE PLAN REVIEW ROUTED |
THROUGH INCOMING GD |