Miscellaneous Information / Notes |
ADDING 866SQFT OF ADDITION |
|
|
|
|
|
|
|
5/11/17 CHANGE CONTRACTOR PAID $100 NATALEE |
5/9/17 CALLED LEFT A MESSAGE TO P/U PERMIT. PLAN |
UP FRONT IN LARGE BIN (V) HM. |
5/5/17 RESUB ADDRESSING DENIED COMMENTS NO FEES GD |
4/17/17 PLAN DENIED CALLED REN. PLAN IN BACK IN |
LARGE BIN (V) HM. |
04/14/2017 PASSED B, SENT TO E (JL). CT |
4/10/17 CUSTOMER BROUGHT PLANS BACK FROM IMPACT |
FEES ROUTED THROUGH INCOMING GD |
4/6/17 CUSTOMER SIGNED OUT 1 SET OF PLANS FOR |
IMPACT FEES GD |
04/05/2017 IN SMALL DENIED V, INFORMED CONTACT. CT |
4/4/17 RESUB ADDRESSING DENIED COMMENTS NO FEES GD |
03/30/2017 IN SMALL DENIED V, INFORMED CONTACT. |
REMOVED FROM BOARD R22. CT |
3/15/17 PLUMB APPROVED RETURN TO R22/GPJ |
3/3/17 COMBINED OLD PLANS WITH NEW; SENT TO |
INCOMING FOR REVIEW RES |
3/1/17 RON REQUESTED CHANGE OF CONTRACTOR NO FEE |
PERMIT HAS NOT BEEN ISSUED AND ADDRESS DENIED |
COMMENTS SHOLDER |
2/24/17 NEED TO INVESTIGATE PROJECT ACTIVITY ON |
RHONDA'S DESK RES |
7/7/16 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
RESUBMIT, FILED UNDER SMALL DENIED "E". CP |
7/1/16 FAILED B, R & IMPACT, SENT TO M (JV). CST |
6/30/16 FAILED ELECTRICAL REVIEW AS NOTED. WALKED |
FILE TO CT FOR BLDG. REVIEW. MA |
6/14/16 - HPD AND ZONING APPROVED, RETURNED TO |
LIBRARY. DLE |
6/10/16 SENT TO ZONING. LEM |