Miscellaneous Information / Notes |
INTERIOR DEMO AND FOUNDATION FOR NEW EXIT STAIRS. |
ADDITIIONAL PLANS AND PERMIT REQUIRED FOR NEW |
STAIRS PRIOR TO START OF CONSTRUCTION UNDER NEW |
PERMIT. |
|
|
|
12/09/16 NADINE P/U PERMIT SPALMER |
11/28/2016+ IN LARGE DENIED BIN "R" RES |
11/28/2016 PERMIT WILL NOT BE ISSUED UNLESS |
RESIDENT INSPECTOR IS SUBMITTED ALONG WITH FIRE |
WATCH PLAN PER CT NO EXCEPTIONS RES |
11/28/2016 IN LARGE DENIED TBD, INFORMED CONTACT. |
CT |
11/23/16 RESUB ADDRESSING DENIED COMMENTS NO FEES |
GD |
08/22/2016 READY, IN LARGE TBD, INFORMED CONTACT. |
CST |
DESCRIPTION AND NOTES ADDED 8/22/16 DH |
8/16/16 PASSED BY FIRE, FORWARDED TO BUILDING.PML |
8/12/16 RESUB ADDRESSING COMMENTS ASM |
7/26/16 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
RESUBMIT, FILED UNDER LARGE DENIED "TBD". CP |
7/28/16 DEMO APPROVED. RE-SUBMITTAL REQUIRED. |
SENT TO ZONING (AM). CST |
7/28/16 DESCRIPTION MODIFIED SO PERMIT CAN |
CONTINUE. THIS PHASE OF THE PERMITTING IS FOR |
EXPLORATORY DEMOLITION SO THE FINAL DESIGN AND |
DRAWINGS CAN BE COMPLETED, INCLUDING STAIRS, LIFE |
SAFETY, SPRINKLER, ELECTRIC, FIRE ALARM, RESIDENT |
INSPECTOR, SHOP DRAWINGS AND FINAL VALUATION NEEDS |
TO BE MADE FOR ADJUSTMENT OF PERMIT FEES. DH |
|
7/27/16 PLUMB APPROVED SENT TO CT/ GPJ |
7/20/16 THE VALUE OF THIS PROJECT REMIANS TOO LOW |
AND NEEDS TO VERIFIED.PML |
|
7/20/16 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
C02.PML |
7/18/16 RESUB ADDRSSING DENIED COMMENTS NO FEE *** |
CUSTOMER REQUESTED EXPEDITE PLAN REVIEW*** NSD |
6/16/16 DH HAS PLANS PREPARING FOR 1:30 MEETING |
6/15/16 PLUMB FAILED IN SMALL TBD DENIED EMAIL |
CUST. /GPJ |
6/15/16 FAILED B, SENT TO E (MARIO). CST |
6/9/16 THE VALUE IS TOO LOW AND NEEDS TO BE |
PROPERLY ADJUSTED BY APPLICANT.PML |
6/9/16 PASSED BY FIRE WITH PROVISO COMMENTS, |
FORWARDED TO BUILDING.PML |
05*25*16 ***CUSTOMER STATED ORIGINAL PLANS ARE BE |
REPLACED*** RESUB ADDRESSING DENIED COMMENTS NO |
FEE NSD |
3/24/16 FAILED FIRE SENT TO SMALL FAILED UNDER |
TBD.PML |
3/18/16 FAILED B, SENT TO FIRE. CST |
3/9/16 PLANS IN LIBRARY WAITING ON CUSTOMER TO ADD |
PAGES, OK PER DHARVEY. CP |