Miscellaneous Information / Notes |
PARKING LOT PERMIT AS REQUESTED (SEPARATE PERMIT |
REQUIRED FOR STRIPING) |
|
|
|
|
5/31/17 KEITH P/U PERMIT CARD SPALMER |
3/23/17 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
DOWNLOAD PLANS, PAY FEES & PICK UP PERMIT CARD. CP |
3/22/17 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
RESUBMIT. CP |
3/7/17 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
3/7/17 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. LEM |
1/12/17 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
1/10/17 RECEIVED UPDATED APPLICATION PER SHILL |
REQUEST, ADDED VALUE TO PERMIT. LEM |
12/15/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
REUSBMIT. LEM |
12/14/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
11/28/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
RESUBMIT DIGITAL SIGNATURES, INVITED TO DO SO. CP |
10/25/16 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
CP |
10/19/16 EXTENSION REQUESTED. CP |
9/30/16 PERMIT EXPIRING SOON EMAIL SENT. CP |
6/29/16 RESUBMIT REMINDER SENT. CP |
4/18/16 RESUBMIT REMINDER SENT. LEM |
3/16/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
RESUBMIT. CP |
1/19/16 PLANS UPLOADED, INCOMING COMPLETE. LEM |
1/13/16 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
FEES. LEM |