Miscellaneous Information / Notes |
#112/114/116 TENANT BUILDOUT FOR SLOANS ICE CREAM |
MFG FACILITY |
|
10/15/15 SEE BUILD. FINAL INSPECTIONS FOR |
CONDITIONS OF THE TCO REQUESTED. A LANGE 3692 |
10/1/15 RECEIVED AND APPROVED LETTER PER RAB |
COMMENT OF 9/28/15. SAK |
9/28/15 SUBMITTED ONM&J STRUCTURAL REVIEW OF |
GROUND FLOOR SLAB REINFORCEMENT MUST BE SUPPORTED |
BY A LETTER OR REVISED PLAN FROM THE ARCHITECT OR |
RECORD. SENT EMAIL TO DALE HEDRICK AND SEAN |
KAUFFMAN. IN SMALL DENIED BIN UNDER "H". RB |
07/13/2015 SEAN P/U PERMIT NSD |
7/13/15 - CONDITIONAL APPROVAL FOR ELECTRIC AS |
NOTED. CONTRACTOR NOTIFIED VIA PHONE. SENT TO SAK |
FOR INCOMMING. MA |
7/6/15 - FAILED ELECTRICAL REVIEW. CONTRACTOR |
NOTIFIED VIA EMAIL. SENT TO LARGE DENIED BIN "H". |
MA |
7/2/15 MOVED TO TKL DESK, SAK |
06/29/15 EARLY START AUTHORIZATION LETTER P/U BY |
SEAN ASM |
6/26/15 PASSED BY FIRE PREVENTION, RETURNED TO |
B07.PML |
6/26/15 MECH PASSED/RETURNED TO B7/CC |
6/24/15 EMAILED DALE AND SEAN TO P/U EARLY START |
AUTHORIZATION LETTER. LETTER FILED FOR P/U UNDER |
"H". RB |
6/24/15 PARTIAL PAYMENT MADE BY SEAN 2.333.38, MS |
6/22/15 RESUB ADDRESSING DENIED COMMENTS NO FEE |
SPALMER |
6/22/15 REQUEST FOR EXPEDITED ROUTED THROUGH |
INCOMING SPALMER |
6/16/15 - FAILED ELECTRICAL REVIEW. CONTRACTOR |
NOTIFIED VIA EMAIL. SENT FILE TO LARGE DENIED BIN |
"H". MA |
6/12/15 FIRE INSPECTOR OBSERVED WORK WITHOUT AN |
ISSUED PERMIT - 4X FEE ASSESSED. JW/WJ |
6/8/15 DENIED BY MECH/ RETURNED TO B22 |
5/27/15 FAILED BY FIRE PREVENTION WITH COMMENTS, |
RETURNED TO B22.PML |
5-20-15 *EXPEDITE REQUEST ROUTED INTO INCOMING* |
SEAN KAUFFMAN WAS UNAWARE HE NEEDED TO PAY PLAN |
REVIEW FEES AT TIME OF SUBMITTAL. HE IS GETTING |
CHECK & WILL PAY TOMORROW ..FIRE ALARM, SPRINKLER, |
WALK-IN COOLER FEES DEDUCTED FROM CONTR VALUE WL |