Miscellaneous Information / Notes |
VISITOR CENTER - 3-STORY BUILDING UTILIZED TO |
SUPPORT FUNCTION OF WASTE TO ENERGY FACILITY |
|
|
|
7/19/16 CO ISSUED EMAILED TO MIKE, SENT TO |
SCANNING AND ORIGINAL IN BOX UNDER "H" |
7/19/16 REQUEST FOR CO FROM MIKE SANCHEZ |
6/5/15 FEE PAID ON TCO AND PICKED UP BY RICHARD. |
LWL |
6/2/15 TCO REQUEST SUBMITTED AND ROUTED TO KCONRAD |
SEW |
02/17/15 JESSICA P/U STOCKING CERTIFICATE NSD |
2/11/15 ISSUED STOCKING CERTIFICATE. TO CO BOX, |
"H". OWES $500.00.CALLED TAMMY FOR P/U.KC |
1/23/15 PLANS IN FILENET. CP |
12/4/14 TCO ROUTED TO KEN CONRAD. LWL |
11/26/14 FILES IN FILENET. CP |
4/10/13 CHANGE OF CONTRACTOR JM |
3/15/13 RECEIVED PEDDS DOCS. PERMIT PRINTED AND |
P/U BY MIKE SANCHEZ. RJR |
3/13/13 PER APPLICANT REQUEST, ICF WALL SHOP |
DRAWINGS ADDED TO THE PROJECT FOR REVIEW. RJR |
2/28/13 PRESCREEN PASSED REVIEW DISTRIBUTED |
APPLICANT NOTIFIED VIA EMAIL CP |
1/10/13 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
APPLICANT NOTIFIED VIA EMAIL. RJR |
11/22/12 RESUBMIT RECEIVED. REVIEWS ASSIGNED. RJR |
10/9/12 REVIEWS COMPLETE. RESUBMIT REQUIRED. |
APPLICANT NOTIFIED VIA EMAIL. RJR |
8/21/12 PLANS UPLOADED. REVIEWS DISTRIBUTED. RJR |