Miscellaneous Information / Notes |
ADDITION TO BACK OF HOUSE RENOVATE KITCHEN POWDER |
ROOM MASTER BATH AND MASTER CLOSET |
|
|
|
|
|
2-9-11 NOC SUBMITTED INSPECTION HOLD RELEASED WL |
1/24/11 FEES PAID PERMIT P/U BY SEAN TSJ |
1/21/11 TALKED TO SEAN. PERMIT PACKAGE UPFRONT IN |
LARGE PLANS SHELF UNDER "C". JG. |
1-14-11 3RD RESUB "ROOFING" WL |
01/04/11 TALKED TO TOMMY TAVERAS (ENGINEER) TO GO |
OVER COMMENTS. JG. |
01/03/11 TALKED TO CONTRACTOR. PERMIT PACKAGE ON |
BACK FILE LARGE PLANS SHELF UNDER "C". JG. |
12/27/10 DID NOT ISSUE PERMIT, 2ND RESUB SMH |
12/10/10 TALKED TO CONTRACTOR. PERMIT PACKAGE |
UPFRONT IN LARGE PLANS FILE UNDER "C". JG. |
12/10/10 TALKED TO MARK (ARCHITECT) TO GO OVER |
COMMENTS. JG. |
12/9/10 REVIEWED AND RETURNED TO JG. J.PAPA. |
12/9/10 SENT TO J. PAPA'S DESK. CONTRACTOR DIDN'T |
SUBMITTED THEM FOR REVIEW/APPROVAL. JG. |
11/16/10 1ST RESUBMITTAL LM |
10/27/10 TALKED TO STRUCTURAL ENGINEER TO GO OVER |
COMMENTS. JG. |
10/26/10 TALKED TO MECHANICAL ENGINEER TO GO OVER |
COMMENTS. JG. |
10/21/10 TALKED TO CONTRACTOR. PLANS ON BACK FILE |
UNDER "C". JG. |