Miscellaneous Information / Notes |
CHANGE OF OCCUPANCY TO DAYCARE INCLUDING INSTALL |
DRIVEWAY, ACCESSIBILITY RAMPS, INTERIOR |
RENOVATIONS |
|
|
|
6/24/2011 - CLOSED PERMIT AND ISSUED CO PER RBROWN |
- DRF |
|
1/3/11 RETURNED TCO REQUEST FORM TO OWNER TO GET |
G.C. TO SIGN. OK TO PRINT AND ISSUE TCO WHEN OWNER |
HAS GOT G.C. SIGNATURE ON THE FORM AND PAYS $500 |
FEE. RB |
12/28/2010 PROCESSED CHANGE OF CONTRACTOR FROM |
ATLANTIDA TO SHORELINE UNDERGROUND SERVICES, INC. |
DBW |
12/1/10 RECEIVED QUALIFIER LETTER TO CLOSE PERMIT |
SINCE HE WILL NOT BE FINISHING THE PROJECT. THE |
PROJECT REQUIRES REVISED PLANS AND FINAL |
INSPECTIONS.PERMITS TO BE APPLIED FOR BY OTHER.KC |
11/29/10 SPOKE WITH THE QUALIFIER, RENE AND HE |
ADVISED ME THAT HE WILL BE SUBMITTING A LETTER TO |
CLOSE THIS PERMIT SINCE HE IS WITHDRAWING FROM THE |
JOB.KC |
6/22/10 NOC SUBMITTED AND UPDATED INSPECTION HOLD |
RELEASED SEW |
5/25/10 PERMIT/PLANS PU BY RENE NEEDS NOC HOLD ON |
INSPECTIONS TILL WE RECEIVE SEW |
5/19/10 PERMIT FILED UNDER 'A' (LARGE BIN) LM |
5/19/10 CHANGE OF CONTR FORM SUBMITTED W/NEW APPL |
$100 ROUTED TO LMARTINEZ SEW |
5/17/10 PLANS IN LUIS'S OFFICE WAITING FOR |
CONTRACTOR CHANGE LM |
4/28/10 PLANS ARE RIDING WITH #09010345 LM |
11/12/09 OK TO P/U ONE SET OF PLANS PER CLARA FROM |
3-D HOMES SPOKE WITH SANDY (ACTING SUPERVISOR) |
MMILLER |
10/31/09 DENIED PLANS FILED UNDER 'T' LM |
10/07/09 PLANS RETURNED TO CSD FROM FIRE; IN B-3 |
MAW |
10/06/09 PLANS TRANSFERRED TO FIRE PREV. BUREAU |
FOR REVIEW TO BE CONDUCTED BY FIRE MARSHAL |
CARSILLO. MAW |
09/29/09 RETURNED TO B3 SLOT RAK |
|
|
|
|
|