Miscellaneous Information / Notes |
PHASE 2 INCLUDING HVAC UNITS PLUMBING & FLAT WORK |
PHASE 1 PERMIT 07060707 |
|
|
|
|
|
10/22/09 FEES PAID MECH REV PU BY ROSE SEEW |
10/21/09 MECH REVISION PASSED, CALLED FOR P/U. |
SPOKE TO ROSE. EXPEDITED REVIEW FEE OF $170 TO BE |
PAID AT TIME OF PICK-UP. SM PLAN UNDER "A" RJR |
10/21/09 TWO HOURS ADDED TO EXPEDITED REVIEW FEE |
FOR MECHANICAL. RJR |
10/20/2009 MECHANICAL REVISION # 02 FEES $110.00 |
ALSO RCVD REQUEST FOR " EXPEDITED PLAN REVIEW |
ROUTED TO LUIS MARTINEZ'S DESK MMILLER |
10-13-09 ROSE PICKUP MECH/ELEC/PLUMB REV (DATED |
10-1-09) WL |
10-8-09 CALLED FOR REVISION P/U AND SPOKE TO ROSE |
K. INDICATING THE REQUIREMENT FOR THE RECEIPT OR |
BLUE CARD AND FEE ($510.00) DUE. "A" KSTEVENS. |
10-8-09 2 HRS EXPEDITED PLMG REVIEW ADDED. |
KSTEVENS. |
10/8/09 TED DAVIS PICKED UP MECH. REVISION SHEETS |
ONLY LM |
10/2/09 TWO HOURS ADDED TO EXPEDITED REVIEW FEE |
FOR MECHANICAL. RJR |
10/2/09 2HRS ADDED FOR EXPEDITED ELEC DV PALMER |
10/01/09 REQUEST FOR EXPEDITED PLAN REVIEW GIVEN |
TO LUIS MARTINEZ SPALMER |
10/01/09 ELEC/PLUMB/MECH $350 SPALMER |
9/28/09 NOC SUBMITTTED AND UPDATED SEW |
9/23/09 ALL PLANS PUT ON LM DESK FOR PROCESSING ES |
9/23/09 NEW PLANS FROM TED WERE DELIVERED TO ERIC |
ALONG WITH SUBMITTAL PACKAGE FROM (LARGE BIN) LM |
9/18/09 PLANS UDNER "A" (LARGE BINS) IN BACK FOR |
CORRECTIONS. CALLED AND SPOKE TO ROSE KENNY. SHE |
WAS AWARE OF COMMENTS. DV PALMER. |
8-27-09 1ST RESUB NO FEE "RESUB" WL |
8-5-09 CALLED CONTRACTOR TO INDICATE PLAN REVIEW |
FINISHED AND THAT THE COMMENTS CAN BE ACCESSED ON |
LINE. SPOKE TO JULIE AT ANDERSON MOORE. "A-LARGE" |
KSTEVENS. |
07/14/2009 DENIED PLANS PLUS APP P/U BY ROSE |
MMILLER |
07/08/09 [email protected] / ENG REVIEW NOT |
REQUIRED FOR THIS SUBMITTAL. |
|