Miscellaneous Information / Notes |
CONSTRUCTION OF NEW WACHOVIA BUILDING |
|
|
3/13/12 3RD TCO P/U BY DAVID TSJ |
12/19/09 3RD TCO ISSUED. TO CO BOX "R".KC |
12/16/09 REQUEST FOR TCO GIVEN TO KEN CONRAD |
SPALMER |
11/23/09 CUSTOMER CALLED. PLACED FILIE IN DENIED |
DRAWER.---RAK |
11/19/09 ISSUED 2ND TCO.KC |
11/18/09 TEMP CERTIFICATE OF OCCUP $500 SPALMER |
10/19/09 TEMP CERTIFICATE OF OCCUP $500 SPALMER |
10/14/09 NEYITA LEIVA P/U REV DATED 9/9/09 SPALMER |
9-23-09 ISSUED REVISON IS FILED UNDER ""R" SMALL |
PLAN CALLED CONTRACTOR JW |
9/22/09 BLDG REV $80 SPALMER |
9/21/09 VICKY P/U ELEC REV DATED 8/25/09 SPALMER |
9/17/09 MECH REV $110 SPALMER |
9-17-09 CALLED NEYITA REVISION FILED UNDER "R" |
SMALL PLANS JW |
9/9/09 BLDG REV $50 PAID SHEETS UNDER THE SITE |
PERMIT SO ONLY $50 IS BEING CHARGED PER |
DVPALMER/SPALMER |
9/7/09 ADDED FEES FOR EXPEDITED REVIEWS FOR MECH |
AND ELEC. BALANCE DUE. CALLED AND SPOKE TO NEYITA. |
OWES FOR REVISION FEE ALSO. REVISION UNDER "R", DV |
PALMER. |
9-02-09 VICKIE IN LOBBY PICKED UP ARCH BLDG |
REVISION JW 9-03-09 |
9/2/09 BLDG REV # 7 $140 STOREFRONT MANUF CHG SLS |
8/27/09 REQUEST FOR OVERTIME INSPECTION FOR FRIDAY |
AUGUST 28 2009 GIVEN TO KEN CONRAD SPALMER |
8/27/09 REQUEST FOR EXPEDITED PLAN REVIEW GIVEN TO |
LUIS MARTINEZ SPALMER |
8/25/09 BLDG REV ARCH ALUMINUM $260 SPALMER |
8/18/09 VICKY P/U REV DATED 8/6/09 SPALMER |
8-10-09 CALLED CONTRACTOR SPOKE WITH NEYITA 2 |
REVISIONS : |
REV 1) PASSED FILED OUT FRONT UNDER "R" SMALL PLAN |
JW |
REV 2) DENIED OWES FEES FILED BACK BINS "R"SMALL |
JW |
8/6/09 BLDG SUBMITTAL STORE FRONT MANUFACTURE |
CHANGE NO FEE SPALMER |
8/6/09 BLDG REV $230 SPALMER |
7/23/09 VICKY P/U REV DATED 6/16/09 SPALMER |
7/22/9 REVISION READY FOR PICKUP, PASSED PORTION |
OF REVISION TO BIG BIN 'R' SMH |
6/16/09 REV ALL TRADES $1040 SPALMER |
6/10/09 PU BY ANDY SEW |
6/10/09 PLANS UNDER "R" FOR PU. LARGE BROWN |
BINS,CALLED AND SPOKE TO ANDY. DV PALMER |
6/2/09 LIGHT POLE CALCULATIONS SUBMITTED UNDER |
WRONG PERMIT, SEE 09020219 LM |
5/28/09 ELEC REV $80 SPALMER |
4/29/09 REVISION $560 SPALMER |
04/20/2009 PERMIT PLUS P/U BY ANDREW MMILLER |
4/16/09 CALL TO P/U PERMIT UNDER 'R' LARGE BIN |
MJACOBS. |
4/10/09 ADDED ADDITIONAL 3HRS FOR BLDG REVIEW. |
CALLED AND SPOKE TO NEYITA. DV PALMER. |
4/2/09 EXPEDITED REQUEST: SPOKE TO DOLORES. GAVE |
ESTIMATED FEES AND COMPLETION DATE. FEES HAVE BEEN |
ADDED (8 HOURS ADDED TO PREVIOUS TOTAL OF 11 |
HOURS) TO PERMIT. REVIEWS WILL BE DISTRIBUTED ONCE |
FEES ARE PAID. RJR |
4/1/09 EXPEDITED PLAN REVIEW REQUEST SUBMITTED AND |
ROUTED TO RREGUEIRO SEW |
4/1/09 PLANS/APPL BROUGHT BACK & ROUTED TO |
INCOMING FOR FURTHER REVIEW 1ST RESUB NO FEE SEW |
4/1/09 PLANS/APPL WAS PICKED UP ON 3/12/09 FOR |
IMPACT FEE PROCESSING SEW |
02/26/2009 1ST RESUB PLANS PLUS APP NO FEE MMILLER |
2/17/09 APP/PLANS P/U BY VICKY SLS |
2/13/09 PLANS FILED UNDER 'R' (LARGE BIN) LM |
2/6/09 EXPEDITED REVIEW: SPOKE TO NEYITA. GAVE |
ESTIMATED COMPLETION AND ESTIMATED FEES. FEES |
ENTERED INTO SYSTEM. RJR |
2/5/09 EXPEDITED REQUEST GIVEN TO RON REGUIERO |
SPALMER |