Miscellaneous Information / Notes |
REMOVE & REPLACE FUEL TANKS LINES AND DISPENSERS |
WITH MISC CONCRETE WORK |
|
|
|
|
|
|
|
7/8/09 ANTHONY P/U ELEC REV DATED 6/30/09 SPALMER |
7/4/09 ELEC REVISIONS ARE UNDER "U" (SMALL). |
CALLED AND LEFT MESSAGE ON PINNACLE DEVELOPMENT'S |
GENERAL VM FOR ANTHONY. REMINDED OF BLUE CARD TO |
PICK UP PLANS. DV PALMER. |
6/30/09 NEW NOC FOR NEW CONTRACTOR TURNED IN TODAY |
SPALMER |
6/30/09 ELEC REV $110 SPALMER |
6/30/09 CHANGE OF CONTRACTOR $100 SPALMER |
6/15/09 ELEC REV FROM 6/2 UNDER "G" (SMALL)FOR |
PICK UP. CALLED AND SPOKE TO ANTHONY AND REMINDED |
OF BLUE CARD. DV PALMER. |
6/2/09 ELEC REV $170 SPALMER |
06/02/2009 APPROVED BLDG APPROVED/DENIED |
ELECTRICAL APPROVED MECHANICAL APPROVED ZONING & |
APPROVED FIRE THAT WAS SUBMITTED ON 05/06/2009 WAS |
P/U BY ANTHONY MMILLER |
05/22/09 RVSD PLANS READY FOR P/U; LARGE BIN "G" |
MAW |
05/06/2009 BLDG ELECTRICAL PLUMBING MECHANICAL |
ZONING & FIRE REVISION # 01 FEES |
|
02/11/09 - EXTEND PERMIT TO 5/15/09 PER RAB - DRF |
|
08/15/08 PERMIT P/U BY ANTHONY JREYES |
13/08 PERMIT READY TO PRINT, UNDER(G)**LARGE |
BINNS** WORKERS COMP EXPIRED, SPOKE TO BLAKE |
ADARROUGH |
07/16/2008 1ST RESUB PLANS PLUS APP NO FEE |
MMILLER |
07/16/08 PU BY ANTHONY SEW |
07/02/08 CALLED FOR P/U "G" LARGE BIN MRW |