Miscellaneous Information / Notes |
PUBLIX #821 INSTALL 500 KW STANDBY GENERATOR |
SYSTEM |
|
|
|
|
3-4-2010 - PERMIT RENEWED NEW EXP DATE 9/4/2010 |
DRF |
3-4-10 BILLY COLLINS PICKUP APPROVED RENEWAL LTR |
WL |
3-4-10 LTR REQUESTING RENEWAL ROUTED TO D FULCHER |
WL |
6/2/09 ELEC LETTER SUBMITTAL PER JAKE LEAHY SLS |
9-5-08 DENNIS DAVIS PICKUP PERMIT WL |
9/4/08 CALL FOR P/U, UNDER(P), CONTRACTOR STATE |
LIC EXPIRED, SPOKE TO DENNIS DAVIS ADARROUGH |
9/2/8 TO MM DESK SMH |
8/29/8 TO MAW DESK, NEEDS TO PASS FIRE SMH |
8/21/8 REMOVED FROM BIN FOR ELECTRIC AND FIRE |
REVIEW DVP |
8/20/8 CALLED CUST, 'P' MM |
8/20/8 TO MM DESK SMH |
7/24/08 4TH RESUB W/PLANS & APPL $198 SEW |
06/20/2008 DENIED PLANS PLUS APP P/U BY DENNIS |
MMILLER |
|
06/20/08 CALLED FOR DENIED PLANS P/U UNDER "P" |
MAW |
05/19/08 3RD RESUB W/PLANS & APPL SEW |
05/19/08 PU BY DENNIS SEW |
04/29/08 CORRECTIONS NEEDED CALLED CONT LEFT MSG |
FILED UNDER "P" SLS |
04/29/8 TO SLS DESK SMH |
04/01/08 2ND RESUB PLANS/APP $198 SLS |
01/08/08 LUCY P/U DENIED PLANS SPALMER |
09/24/07 CALLED FOR DENIED PLANS P/U UNDER "P" |
MAW |
08/03/07 CONTRACTOR CAME IN PAID FEES $1975.80 |
CHGD FROM HOLD STATUS TO OPEN FORWARDED TO |
INCOMING |
SLS |
07/03/07 PLANS PULLED FROM THE REVIEW PROCESS. THE |
FEES WHICH WERE OWED WERE DUE NO LATER THAN 5PM ON |
7/2/07. SPOKE TO LUCIANNA AND RACHEL FROM |
STATEWIDE PERMITTING TWICE THE WEEK BEFORE AND WAS |
TOLD FEESE WOULD BE PAID. THE FEES WERE NOT PAID, |
SO THE RESUB DATE WILL START AGAIN WHEN THE FEES |
ARE PAID. PLANS ARE UNDER "P" ON HOLD AND ARE NOT |
TO BE RELEASED. DV PALMER. |
6/19/07 VALUE ADJUSTED, OWES FEES AT THIS TIME. |
PROJECT IS BEING PLACED ON HOLD UNTIL FEES ARE |
PAID. PLANS WILL NOT BE REVIEWED AND WILL BE |
REMOVED FROM REVIEW PROCESS IF FEES OF $1975.80 |
ARE NOT PAID BY 6/27/07. DV PALMER. |
|
05/22/2007 1ST RESUB PLANS PLUS APP NO FEE |
MMILLER |
12/07/06 PLANS PLUS APP P/U BY VICKY MMILLER |
12/5/06 CALL FOR P/U LEFT MESSAGE(P) ADARROUGH |