Miscellaneous Information / Notes |
BUILD FELLOWSHIP HALL (ADDITION) |
|
****** EXPIRED****** |
|
10/30/06 SHARYL P/U DENIED PLANS SPALMER |
10/26/06 CONTRACTOR DID NOT WANT TO APPLY FOR AN |
EXTENSION. OVER SIX MONTHS OF NO ACTIVITY. SPOKE |
TO NEIL MELICK CONTRACTOR WAS GIVEN TWO OPTIONS, |
ONE TO APPLY FOR EXTENSION HOWEVER REVIEW COMMENTS |
AND FINES WOULD APPLY OR TO LEAVE AS EXPIRED AND |
WOULD HAVE TO RE-DESIGN PROJECT UNDER THE 2004 |
FBC, RE- APPLY AND PAY PERMIT FEES UNDER NEW |
APPLICATION. |
SPOKE TO ALFONS NEWBOLD OF NEW BOLD CONTRUCTION |
AND THE "DESIGNER" MARK AND BOTH AGREED TO BE |
"EXPIRED". ONE SETS OF PLANS WILL REMAIN WITH THIS |
OFFICE FOR FILE ON DESIGN PROFESSIONAL PER NEIL |
MELICK AND DV PALMER. THE OTHER SET IS UNDER "N" |
IN THE LARGE BINS FOR PU. DV PALMER. |
|
10/25/06 ON HOLD PER NEIL. SEE DVP. DV PALMER |
10/3/06 3RD BLDG RESUB W/ORG APPL. $147 TA |
********************************************** |
******************************************** |
******************************************* |
2/9/05-CALL FOR P/U UNDER (N)ADARROUGH |
6/27/05 1ST RESUB PLANS + APP PT |
8/5/05 CALL FOR P/U FILE N MM |
8-5-05 ALFONSO NEWBOLD PICKUP PLANS WL |
12/30/05 2ND RESUB $147 FEE. LTM |
************************************************** |
1/31/06 4X FEE ACCESSED FOR PLAN REVIEW,$1,764.00 |
MUST BE PAID BEFORE RESUBMITTING PLANS FOR 4TH |
REVIEW. DV PALMER. |
2/8/06 UNITY OF TITLE THE NEW PCN = |
74434321060230120 : CHANGED THE PERMIT TO MATCH |
THE NEW ADDITION .ADDRESS REMAINS THE SAME:909 3RD |
ST.LU |
2-18-06 DENIED CALLED P/U "N" PES |
2/21/06 SHARYL P/U DENIED PLANS SPALMER |