Miscellaneous Information / Notes |
1ST FLOOR RETAIL AND 2ND-3RD FLOOR APARTMENTS |
BLDG G - 3 APARTMENTS AND 2 RETAIL UNITS |
|
|
|
|
|
4/7/06 EXTENSION OF TCO $500 SPALMER |
3/27/06 EXTENSION OF TCO $500 SEW |
************************************************* |
************************************************* |
2/10/06 TCO ISSUED HHP |
11-19-03 DENIED. CALLED FRANK PEPE FOR P/U.'I'. RB |
11/20/03 BARRY UNDERWOOD P/U DENIED APPL.SH |
12/24/03 1ST RESUB/NO FEE/BLDG/ELEC/MECH/PLUMB.SH |
1-16-03 DENIED. CALLED FOR P/U. 'I'. RB |
1-20-4 PLANS PU/BARRY - KAM |
2/9/04 2ND RESUB BZ237148 PSMITH |
2-26-04 **OWES FEE** CALLED FRANK FOR P/U.'I'.RB |
4/13/04 FRANK PEPE P/U PERMIT SPALMER |
6-30-04 REV #1 $560 BZ 243275 ROLLED PLANS PLUS |
"KINKO'S BOX WL |
7-23-4 CALLED FOR P/U "I" KSTEVENS |
8-19-04 REVISION $120 NFL |
8/30/04 GIVEN TO JOHN ROACH, PLANNER 822-1448 |
8/30/04 APPROVED JOHN ROACH, PLANNER 822/1448 MM |
10/12/04 FRANK PICKED UP PLANS FOR IMPACT FEES LM |
10/12/04 ROBERT BROWN HAS ENERGY CODE FORMS TO BE |
PUT WITH THE PLAN SETS AFTER IMPACT FEES PAID. RB |
10/19/04 RETURN WITH IMPACT FEES PD PR04031396 DR |
10-22-04 CALLED FRANK PEPE FOR P/U. 'I'. RB |
10-26-04 FRANK PEPE P/U PLANS. RB |
3-23-05 TRUSS ENGINEERING SUBMITTAL DENIED. FAXED |
COMMENTS TO 'FLORIDA QUALITY TRUSS' AND CALLED |
FRANK PEPE TO P/U PLANS.'I'.RB |
3-24-05 BARRY P/U PLANS NFL |
3/28/05 SUBMITTAL SHOP DRAWINGS NO. P FEE SPALMER |
3/28/05 DENIED. CALLED FRANK. PLANS WITH R BROWN |
AWAITING REVISED CALCULATIONS FOR TRUSS DESIGN. RB |
4/14/05 STRUCTURAL SUBMITTAL. NO FEE. RB |
4/19/05 CALLED FRANK FOR ARCHITECTURAL AND |
STRUCTURAL SUBMITTAL P/U PER REVIEW NOTES. 'I'. RB |
4-26-05 CALLED FRANK FOR TRUSS SUBMIT'L P/U.'I'.RB |
5-4-05 P/U TRUSS DRAWINGS NFL |
10-17-05 REV #3 MECH, REV #4 ELEC, REV #5 SITE |
PLAN PKGS ROUTED TO L MARTINEZ PER FRANK P WL |
11/15/05 SITE PLAN TO JOHN ROACH LM |
ELECT. TO DEWEY |
MECH. TO PATTY |
11-15-05 CALLED FOR P/U UNDER I PHK |
11/21/05 MICHAEL P/U REV SPALMER |
11/21/05 REVISIONS TO SITE PLAN UNCLEAR...MEETING |
WITH CONTRACTOR ON 11/23/05 TO CLARIFY. JPR |
12/2/05 REVISED SITE PLAN APPROVED....GIVEN TO |
MMCLEAN FOR FURTHER PROCESSING. JPR |
12/02/05 APPROVED & GIVN TO INCOMING FOR |
PROCESSING FOR ENGINEER TO REVIEW MM |
12-08-05 CALLED FOR PU, UNDER "I" REVISION, MRA |
12/16/05 REV. P/U BY MICHAEL AJP |
2/10/06 EXTENSION OF TCO 2/6/06 |