| NEW CONST |
| 12/28 DENIED PLANS DO NOT HAVE SUFFICENT CONSTRUCT |
| INFORMATION JC |
| RESUB 5-11-00SG |
| RESUB 7/20/00 SJOHNSON |
| ELECTRICAL STILL NOT ADDRESSED AS OF 8/2/00 DVP. |
| RESUB 2/13/01 BZ179229 $241.50 SJOHNSON |
| RESUB 4/24/01 BZ183968 TR |
| NO MECHANICAL PLANS SUBMITTED. SUBMIT PLANS WITH |
| MECHANICAL PERMIT APPLICATION. PHK 2/22/01 |
| PLANS IN ENGINEERING 3/6/01 DV PALMER |
| PLANS BACK FROM ENGINEERING 3/7/01 TO ZONING. |
| DV PALMER. |
| BACK FROM ZONING 3/20/01 DVP |
| PICKED UP BY GAY CINQUE 3/21/01 TO GO UPSTAIRS. |
| PLANS BACK AND ARE OUTFRONT FOR PICK-UP "R" |
| PLANS P/U EUGENE FAGAN 4/9/01 SJOHNSON |
| RESUB 4/24/01 |
| CALLED FOR P/U 5/9/01 UNDER "R" PHK. RECPT ATTCHD. |
| 5/9/01 EUGENE PU PLANS YD |
| 5/21/01 RESUB FOR BLDG BZ185743 $281.50 YD |
| 5/29/01 RESUB TO PLUMBING LM |
| 06/14/01 PLANS ON JW DESK, OWNER GAVE VERBAL ONLY |
| FOR TERMINATION OF CONTRACTOR, SEE L.MARTINEZ |
| FOR INFORMATION!!!!! JW. |
| CHANGE OF CONTRACTOR 7/3/01 BZ187431 $100 SJOHNSON |
| 7/3/01 SANDY PU PERMIT YD |
| SUBMITTALL SHOP DRAWINGS 12-26-2001 AN |
| 2/27/02 GAY PU PLANS YD |
| 5-22 SUBMITTAL NFL |
| 5/29 CONTR. PICKED UP GLAZING SUBMITTAL, LM |
| REV BLDG $70 BZ207268 7/10/02 SJOHNSON |
| REV FROM 7/10/02, UNSAT, CALLED, UNDER "D" FOR PU. |
| DV PALMER. 7/23/02. |
| 7-24 GAY P/U REVISIONS NFL |
| SUBMITTAL NO FEE 7/29/02 SJOHNSON |
| 8-1 SUBMITTAL NFL |
| SUBMITTAL NO FEE 8/2/02 SJOHNSON |
| 8/19/02 REVISION BZ209912 $110 ALL TRADES YD |
| 8/23/02 CALLED CONT PLANS FILED UNDER "D" JW |
| GAY CINQUE PICK UP BLDG/ELEC/FIRE REV 8-27-02 WL |
| 9/4/02 REVISION BZ210531 FOR ELEC,BLDG $110 YD |
| REVISIONS PU/GAY 9-9-02 KAM |
| SUBMITTAL PU/GAY 9-9-02 KAM |
| 9-16-02 SUBMITTAL NFL |
| 9/17/02 CALLED CONT PLANS FILED UNDER "D" JW |