| Miscellaneous Information / Notes |
| 734 SF PRE MANUFACTURED BUILDING FOR COFFEE SHOP |
| DRIVE THRU |
| |
| |
| |
| |
| 7/19/23 TCO ISSUED, ATTACHED REG |
| 7/11/23 RECEIVED TCO REQUEST FEE NOT APPLIED REG |
| 6/29/23 RECEIVED STOCKING REQUEST ATTACHED, FEE |
| NOT APPLIED REG |
| 3/10/23 PERMIT ISSUED. LEM |
| 3/10/23 PLAN REVIEW COMPLETE,WAITING ON CONTRACTOR |
| UPDATE & APP W OWNER'S SIGNATURE/SIGNED CONTRACT |
| AO |
| 3/6/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 3/6/23 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/27/23 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 2/24/23 IMPACT FEE QUEST UPLOADED. PBCGOV EMAILED |
| PER R MCPHERSON AO |
| 2/24/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT AO |
| 2/15/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT AO |
| 2/6/23 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| AM |
| 1/12/23 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT. EMAIL SENT TO SYBILLE WELTER REVIEW AIPP |
| AO |
| 12/19/22 RECEIVED EXPEDITE REQUEST. LEM |
| 12/19/22 PLANS CORRECTED, INCOMING COMPLETED,CD |
| 12/14/22 REJECTED TASK TO CUSTOMER TO FIX SHEETS. |
| LEM |
| 11/1/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. AM |