| Miscellaneous Information / Notes |
| INSTALLATION OF ONE NEW 12.5 TON ROOF TOP PACKAGE |
| UNITS 1 |
| |
| |
| 2/27/23 RECEIVED REFUND REQUEST. APPROVED REFUND |
| ON MARCH 7TH PER REVISED SCOPE OF WORK. JM |
| 2/17/23 PERMIT ISSUED. LEM |
| 2/17/23 REVISED DESCRIPTION OF WORK, OK PER |
| REVIEWER. LEM |
| 12/29/22 REVIEWS COMPLETE, WAITING ON FEES TO |
| ISSUE PERMIT. LEM |
| 12/16/22 RESUB RECEIVED,INCOMING COMPLETE AO |
| 12/12/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT. CP |
| 11/30/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 10/18/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 9/27/22 RESUB RECEIVED, INCOMING COMPLETE AO |
| 7/24/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 6/17/22 FEES PAID, INCOMING COMPLETE PAPER ROUTED |
| TO MPETERSON FOR SIGNATURE REBVIEW.CD |
| 6/14/22 APPLICANT SENT INVITE TO PAY FEES. PAPER |
| ROUTED TO "FAILED" BOX IN SCANNING.CD |
| 6/8/22 PLANS UPLOADED, WAITING ON FEES. |
| APPLICATION SENT INVITE TO PAY FEES,.CD |
| 6/8/22 CHANGED FROM PAPER TO DIGITAL.CD |