| Miscellaneous Information / Notes |
| PHASE 2 - RENO/REPAIR TO STRUCTURAL, ROOFING, |
| ELEC, PLUMBING, MECH, AND HC CHAIR LIFT, DRYWALL, |
| CABINETRY |
| |
| 6/27/23 ADDED $75 RENEWAL FEE TO 12/27/23 JPB |
| *** CBAA APPLICATION RECEIVED 5/13. FEE PAID. |
| SCHEDULED FOR THE 6/16/22 CBAA MEETING *** |
| 8/2/22 NOTICE OF HEARING AND ORDER, CERTIFIED MAIL |
| RETURNED. |
| 6/16/22 ORDER: THE BOARD AGREES WITH AND ACCEPTS |
| THE CITY'S FINDINGS OF FACT AS PRESENTED AND THE |
| APPLICATION IS GRANTED THEIR REQUEST FOR VARIANCE |
| TO THE FLOOD PREVENTION AND CONTROL ORDINANCE IN |
| ACCORDANCE WITH SECTION 18-286. MOTION CARRIED. |
| |
| |
| 6/3/22 PLANS RELEASED, PERMIT CARD UPLOADED AO |
| 6/3/22 PLAN REVIEW COMPLETE, WAITING ON APP W |
| OWNER'S SIGNATURE OR SIGNED CONTRACT AO |
| 6/3/22 PASSED BY FIRE.PML |
| 6/2/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 6/2/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 5/27/22 PASSED BY FIRE.PML |
| 5/26/22 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 5/18/22 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT. CP |
| 4/29/22 FAILED BY FIRE WITH COMMENTS.PML |
| 4/19/22 PLANS UPLOADED,INCOMING COMPLETE.CD |
| 4/18/22 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |