| Miscellaneous Information / Notes |
| R3 HEALTH -BUILD OUT OF 6000 SF FOR OFFICE SPACE |
| AS PER PLANS |
| |
| |
| |
| 8/23/22 CC ISSUED AND EMAILED TO P. KOLOSVARY. |
| SCANNING FOR FILENET. ATTACHMENT IN C+. FILED |
| UNDER "K". SD |
| 8/19/22 TCO ISSUED AND EMAILED TO P. KOLOSVARY. |
| SCANNING FOR FILENET. ATTACHMENT IN C+. FILED |
| UNDER "K". JB/KP |
| 3/14/22 PERMIT ISSUED. LEM |
| 3/10/22 REVIEWS COMPLETE, WAITING ON UPDATED SUB |
| CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 3/3/22, PASS FIRE, CRW |
| 3/08/2022 RESIDENT INSPECTOR PAPERWORK RECEIVED |
| AND APPROVED CARL FORBES PE |
| 3/2/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 2/16/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 1/31/22, PASS FIRE, CRW |
| 1/28/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 1/28/22 REJECTED, APPLICANT ASKED TO PROVIDE PDF |
| FILES, LINKS ARE NOT ACCEPTED AO |
| 1/14/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 11/30/21, PASS FIRE, CRW WITH PROVISO NOTES, FIRE |
| PROVISO NOTE 1: AN IMPAIRMENT TO A FIRE PROTECTION |
| SYSTEM EXCEEDING 4 HOURS IN A 24- HOUR PERIOD WILL |
| REQUIRE A FIRE WATCH TO BE INITIATED. |
| FIRE PROVISO NOTE 2: ANY WORK CONDUCTED ON THE |
| FIRE SPRINKLER SYSTEM SHALL BE PERFORMED BY A |
| CONTRACTOR LICENSED FOR FIRE PROTECTIONS SYSTEMS. |
| FIRE PROVISO NOTE 3: SHOWER GRAB BAR INSTALLATION |
| SHALL COMPLY WITH NFPA 101 38.2.1.5 |
| |
| |
| 11/29/21 PLANS UPLOADED, INCOMING COMPLETE. LEM |
| 11/12/21 APPLICANT INVITED TO PAY FEES AND UPLOAD |
| PLANS / DOCUMENTS. CC |