| Miscellaneous Information / Notes |
| CONSTRUCTION OF NEW SFR |
| |
| |
| |
| |
| |
| STUDIO SESSION |
| 731-460-650 |
| |
| 12/15/22 CO ISSUED AND EMAILED TO |
| [email protected] |
| SCANNING FOR FILENET. ATTACHED IN C+. FILED UNDER |
| THE LETTER "R". SD |
| 4/8/22 PERMIT ISSUED. LEM |
| 4/7/22 REVIEWS COMPLETE, WAITING ON FEES AND |
| UPDATED CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 3/30/22 IMPACT FEE QUEST UPLOADED. PBCGOV EMAILED |
| AO |
| 2/23/22 - ZONING PASSED. LL |
| 2/16/22 APPLICANT RESUBMITTED DIGITALLY, INCOMING |
| COMPLETE AO |
| 2/16/22 REJECTED, REVISED PLANS WERE NOT |
| VERSIONED. EMAILED APPLICANT TO REUPLOAD. AO |
| 1/20/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 12/9/21- ZONING FAILED. LL |
| 11/23/21 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 10/19/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 10/18/21 DEF. FIELDS COMPLETE. CT |
| 10/18/21 VALUE ADJUSTED TO $240,641.00 PER THE ICC |
| BUILDING VALUATION DATA. CT |
| 9/16/21 - ZONING FAILED. LL |
| 8/23/21 PLANS UPLOADED,INCOMING COMPLETE.CD |
| 7/28/21 REJECTED TASK TO CUSTOMER TO FIX SHEETS. |
| LEM |
| 7/6/21 APPLICANT INVITED TO UPLOAD PLANS OR |
| DOCUMENTS AND PAY FEES. CC |