| Miscellaneous Information / Notes |
| REMOVE AND REPLACE DOCK PILINGS, NEW BOAT LIFT AND |
| PWC LIFT |
| |
| |
| |
| |
| |
| |
| 06/02/2022 CHANGE OF CONTRACTOR $100 SPALMER |
| 5/21/22 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS. CP |
| 5/10/22 REVIEWS COMPLETE, WAITING ON UPDATED |
| CONTRACTOR INFO TO ISSUE PERMIT. LEM |
| 5/10/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 5/4/22 APPLICANT RESUBMITTED DIGITALLY,PLANS |
| VERSIONED,INCOMING COMPLETE AO |
| 4/25/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 04/18/22 THIS SIGNATURE REVIEW IS ONLY FOR HARD |
| COPIES OF ENGINEER DRAWINGS 1 OF 4 THRU 4 OF 4 |
| FROM MCR PROFESSIONAL ENGINEERING, INC. SUBMITTED |
| ON 04/15/22. THESE DRAWINGS HAVE ENGINEER'S |
| EMBOSSED SEAL AND WET SIGNATURE. DWGS ON JULIO'S |
| DESK UNDER "PENDING LAST REVIEW".JG. |
| 4/18/22 RESUB DOCS UPLOADED INTO PROJECTDOX. PAPER |
| ROUTED TO JGOMEZ FOR SIGNATURE REVIEW.CD |
| 04/15/2022 RESUB TO ADDRESS DENIED COMMENTS ROUTED |
| TO INCOMING JO |
| 3/30/22 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. AO |
| 3/17/22 REVIEW OF SIGNATURE ON PAPER PLANS PASSED |
| AND ROUTED TO STORAGE.M.P. |
| 3/17/22 RESUB UPLOADED TO PROJECTDOX, PAPER |
| ORIGINALS ROUTED TO MPETERSON , INCOMING COMPLETE |
| AO |
| 03/16/2022 RESUB TOADDRESS DENIED COMMENTS ROUTED |
| TO INCOMING JO |
| 12/13/21 RECEIVED CHANGE OF CONTRACTOR, NO FEES |
| SINCE PERMIT IS NOT ISSUED. LEM |
| 3/18/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 03/05/21 PLANS UPLOADED, INCOMING COMPLETE AO |
| 03/05/21 UPLOADED TO PROJECTDOX,SCANNIG FEES |
| ADDED. PAPER ORIGINALS ROUTED TO ME AO |
| 03/05/2021 CUSTOMER TURNED IN PLANS FOR US TO |
| UPLOAD SPALMER |
| 3/1/21 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |
| |