| Miscellaneous Information / Notes |
| CONSTRUCTION OF CLUBHOUSE, "AE" FLOOD ZONE- |
| ELEVATION CERTIFICATE REQUIRED |
| |
| |
| 10/7/22 CBAA FEE RELEASED. CO ISSUED AND EMAILED |
| TO FERNANDO BONILLA. SCANNING FOR FILENET. |
| ATTACHMENT IN C+. FILED UNDER "A". KP |
| 10/4/22: CBAA FEE APPLIED TO PERMIT. KP |
| 7/22/22 TCO2 FEE PAID AND CERTIFICATE ISSUED AND |
| EMAILED TO ROBERT HALL. SCANNING FOR FILENET. |
| ATTACHMENT IN C+. |
| 4/29/22 TCO ISSUED AND EMAILED TO ROBERT HALL. |
| SCANNING FOR FILENET. ATTACHMENT IN C+. FILED |
| UNDER "A". KP |
| 6/30/21 ELEV CERT DROPPED OFF IS FOR SUBMITTAL |
| 21060521 AO |
| 6/29/21 ELEVATION CERTIFICATE DROPPED OFF ROUTED |
| TO SCANNING. TSG |
| 3/26/21 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, PERMIT CARD UPLOADED. LEM |
| 3/24/21 REVIEWS COMPLETE, WAITING ON IMPACT FEES. |
| LEM |
| 3/18/21 AIPP REQUIREMENT SATISFIED PER EMAIL |
| S.WELTER SH |
| 3/16/21 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 3/12/21RESUBMIT RECEIVED, INCOMING COMPLETE. CC |
| |
| 2/25/21 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 2/17/21 VALUATION CHANGED FROM $1,100,000.00 TO |
| $1,153,100.00 BASED ON COST BREAK DOWN PROVIDED. |
| RM |
| 1/25/21 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 1/20/21 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 12/11/20 PLAN REVIEW COMPLETE, APPLICANT INVITED |
| TO RESUBMIT. CP |
| 11/25/20 ELECTRICAL REVIEW COMPLETED. FAILED. EQ |
| 11/18/20 PASSED BY FIRE WITH PROVISO COMMENTS IN |
| DIGITAL PLAN REVIEW.PML |
| 10/23/20 FEES PAID, INCOMING COMPLETE. CP |
| 10/19/20 PLANS UPLOADED, WAITING ON FEES. CC |
| 10/15/20 APPLICANTI INVITED TO UPLOAD PLANS AND |
| PAY FEES. LEM |