| Miscellaneous Information / Notes |
| ***SPECIFIC CONDITIONS APPLY SEE ZONING PROVISO*** |
| RESIDENTIAL ADDITION AND REMODEL GARAGE & MASTER |
| BEDROOM REPLACE WINDOWS AND EXISTING DOORS |
| |
| |
| 5/17/23 ABANDONED PERMIT EXPIRED. LAST INSPECTION |
| DONE ON 10/20/2020.CD |
| 7/31/20 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, WAITING ON FEES TO ISSUE PERMIT |
| CARD. LEM |
| 7/31/20 ROUTED IMPACT FEE DOCS TO RECORDS, ROUTED |
| ORIGINAL PLAN PAGE THAT WAS NOT DIGITALLY SIGNED |
| TO STORAGE SH |
| 07/30/2020 ROUTED TO SHILL SPALMER |
| 07/30/2020 RETURNED FROM PAYING IMPACT FEES |
| SPALMER |
| 7/29/20 IMPACT FEE PLAN ON TEQUESTA DESK IN |
| SCANNING ROOM WAITING ON SUBMITTAL FORM TO BE |
| EMAIL BACK TSG |
| 7/22/20 CONTRACTOR P/U 1 SET OF PLANS FOR IMPACT |
| FEES PLACED BACK IN THE DENIED BIN TSG |
| 7/20/20 REVIEWS COMPLETE, APPLICANT INVITED TO |
| RESUBMIT FOR IMPACT FEES. LEM |
| 07/01/20 APPLICANT RESUBMIT UPLOADED. INCOMING |
| COMPLETE. CC |
| 6/2/20 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 05/18/2020 PERMIT CONVERTED TO DIGITAL AND CREATED |
| IN PROJECTDOX, APPLICANT INVITED TO PROJECTDOX. CC |
| 5/18/2020 STOPPED ROUTING THIS PAPER PERMIT; SPOKE |
| WITH CONTRACTOR AND AGREED HE WOULD CONVERT TO |
| DIGITAL; C.CARVAJAL TO HELP HIM GET STARTED WITH |
| PROJECT DOCS; PUT PAPER PACKAGE IN LARGE DENIED |
| "L" RES |
| 5/1/2020 SUBMITTED VIA DROP BOX; ROUTED TO |
| INCOMING RES |
| 03/24/20 APPLICATION DENIED, EMAILED APPLICANT, |
| FILED LARGE DENIED BIN "L"LEM |
| 03/23/20 DENIED BY PLUMBING AND SENT TO |
| PROCESSING, LAC |
| |
| |