| Miscellaneous Information / Notes |
| REMODEL OF 1ST & 2ND FL RESTROOMS |
| |
| |
| |
| 2/27/2020 PG EMAILED CC TO MR WINFREE. ORIGINAL |
| UNDER LETTER "W" GAVE TO SCANNING FOR FILENET. |
| 01/29/2020 DALTON P/UY COC SPALMER |
| 1/29/20 (PG) PRINTED CC-PICKED UP BY DALTON IN |
| FRONT LOBBY. GAVE COPY TO SCANNING FOR FILENET AS |
| WELL. |
| 9/24/19 AMANDA PICKED UP PERMIT BB |
| 9/23/19 EMAILED CONTRACTOR TO INFORM THAT PERMIT |
| IS READY FOR ISSUANCE. 1 CONTRACTOR SET AND OUR |
| FILE SET ARE FILED IN LARGE APPROVED PLANS UNDER |
| "W"LEM |
| 9/23/19 - REVIEW COMPLETED. SENT TO INCOMING. TKL. |
| 9/17/2019 RICHARD RESUB TO ADDRESS DENIED COMMENTS |
| JS |
| 09/10/2019 RICH SIGNED OUT 1 SET OF PLANS PLACED |
| BACK IN LARGE DENIED "W" JS |
| 9/6/19 APPLICATION DENIED, EMAILED APPLICANT, |
| FILED LARGE DENIED BIN "W"LEM |
| 8/15/19 PASSED BY FIRE WITH PROVISO COMMENTS, |
| RETURNED TO C11.PML |
| 8/13/19 RICHARD RESUB ADDRESSIG DENIED COMMENTS BB |
| 06/25/19 TALKED TO ROBERT (ARCHITECT) TO GO OVER |
| TOILET COMPARTMENT W/ SINK AND CORRECT ADDRESS. |
| JG. |
| 06/21/19 TALKED TO ROBERT (ARCHITECT) TO GO OVER |
| COMMENTS. JG. |
| 6/20/19 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "W". CP |
| 06/19/19 DENIED. SENT TO LIBRARY. JG. |
| 6/4/19 PLB COMPLETED AND ROUTED BACK TO C14. TLH |
| 5/13/19 PASSED BY FIRE WITH PROVISO COMMENTS, |
| RETURNED TO C14.PML |