| Miscellaneous Information / Notes |
| NEW PARKING STRUCTURE (18,486SF) W/ OFFICE |
| (1,058 SF) |
| ### RESIDENT INSPECTOR### TICE ENGINEERING |
| |
| |
| |
| 4/23/19 CUSTOMER LEFT CHECK AND TCO AT FRONT |
| COUNTER, PUT TCO W/ CHECK ATTACHED BACK UNDER "A" |
| BEHIND FRONT COUNTER. AM |
| 4/19/2019 TCO PRINTED AND BEHIND FRONT COUNTER |
| UNDER "A" CONTRACTOR NEEDS TO PAY REG |
| 04/18/19 REQUEST FOR TCO ROUTED TO RICHARD |
| GATHRIGHT & SCANNED TO THIS PERMIT SPALMER |
| 12/27/18 PLANS IN FILENET. LEM |
| 10/29/18 REVIEWS COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEEDS TO SUBMIT ORIGINAL |
| APPLICATION, NEEDS TO PICK UP PERMIT CARD. LEM |
| 10/23/18- MECH PASSED W/ PROVISO FOR DEFERRED |
| SUBMITTALS FOR THE PARKING GARAGE SENSORS, AND |
| NOA'S FOR THE LOUVERS AND CONDENSER STAND/CC |
| 9/27/18 PASSED BY FIRE IN DIGITAL PLAN REVIEW.PML |
| 9/25/18 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/28/18 CUSTOMER APPLIED FOR SEPARATE FOUNDATION |
| PERMIT, REMOVED THE FOUNDATION FEE AMOUNT |
| ($114,000) FROM THIS PERMIT AND TRANSFERRED TO |
| 18081379. LEM |
| 8/27/18 REVIEWS COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 7/18/18 FAILED BY FIRE WITH COMMENTS IN DIGITAL |
| PLAN REVIEW.PML |
| 7/11/18 APPLICANT UPLOADED PLANS & PAID FEES. CP |
| 7/11/18 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |