| Miscellaneous Information / Notes |
| RENOVATE EXISTING GAS STATION WITH ELECTRICAL, |
| MECHANICAL, PLUMBING & STRUCTURAL REPAIRS |
| |
| |
| |
| 7/14/22 ISSUED CERTIFICATE OF COMPLETION VIA |
| EMAIL. SIGNED ORIGINAL IN CO BOX UNDER "D". RB |
| 01/20/2022 (PG) JAN 20 2022 CBAA DOCS ATTACHED - - |
| > |
| BOARD GRANTED THE APPLICANT THEIR REQUEST FOR A |
| 6-MONTH EXTENSION TO THEIR TCO, BEGINNING FROM THE |
| DATE OF JANUARY 14, 2022. |
| |
| 9/28/21 (PG) WENT BEFORE THE CBAA ON 9/16/21. |
| CLICK |
| ON "ATTACHMENTS" TO VIEW ALL DOCUMENTS PERTAINING |
| TO CASE NUMBER 1446 - - - - - - > > > > > > > > > |
| |
| 1/20/22 CBAA GRANTED ADDITIONAL 6 MONTH EXTENSION |
| FROM 1/14/22. NEW TCO EXPIRATION DATE: 7/14/22 |
| 9/16/21 CBAA GRANTED ADDITIONAL 120 DAY EXT. NEW |
| TCO EXPIRATION DATE: 1/14/2022 KP |
| 7/1/21 TCO2 EMAILED TO MOHAMMED ISLAM AT |
| [email protected]. SCANNING FOR |
| FILENET. ATTACHMENT IN C+. FILED UNDER "D". KP |
| 6/30/21 SEND REQUEST FOR PAYMENT TCO2. DB |
| 4/2/21 TCO ISSUED AND EXPIRES ON 7/1/21. TCO TO |
| FILENET. DB |
| 3/31/21 RECIEVED TCO REQUEST AND ADDED FEE. DB |
| 8/26/19 MOHAMMAD P/U PERMIT SPALMER |
| 8/20/19 EMAILED CONTRACTOR TO INFORM THAT PERMIT |
| IS READY FOR ISSUANCE. 1 CONTRACTOR SET AND OUR |
| FILE SET ARE FILED IN LARGE APPROVED PLANS UNDER |
| "D"LEM |
| 7/19/19 MOHAMMED RESUB TO ADDRESSED DENIED |
| COMMENTS SL |
| 3/22/19 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "D". CP |
| 3/15/19 PLUMBING COMPLETE AND RETURNED TO B24. TLH |
| 3/8/19 PASSED BY FIRE WITH PROVISO COMMENTS, |
| RETURNED TO B24.PML |
| 02/28/19 MOHAMMAD RESUB TO ADDRESS DENIED COMMENTS |
| BB |
| 01/23/19 MOHAMMAD SIGNED OUT 1 SET OF PLAN BB |
| 1/11/19 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "D". CP |
| 1/8/19 SENT TO ZONING. CP |
| 11/29/2018 MOHAMMED RESUB TO ADDRESS DENIED |
| COMMENTS BB |
| 9/4/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "D". CP |
| 8/30/18 PLUMB DENIED RETURN TO B06/GPJ |
| 8/9/18 PASSED BY FIRE RETURNED TO LIBRARY.PML |
| 8/3/18 MOHAMMED RESUB TO ADDRESS DENIED COMMENTS |
| SHOLDER |
| 6/18/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER LARGE DENIED |
| "D". CP |
| 6/14/18 PLUMB DENIED RETURN TO B01/GPJ |
| 5/25/18 PASSED BY FIRE WITH PROVISO COMMENTS, |
| RETURNED TO B01.PML |