| Miscellaneous Information / Notes |
| INSTALL 20 KW STANDBY GENERATOR ON PRECAST SLAB |
| HOOK TO NEW 500 GALLON BELOW GROUND LP TANK |
| |
| |
| |
| |
| 5/30/18 JONATHAN P/U PERMIT SPALMER |
| 5/23/18 APPLICATION DENIED, EMAILED APPLICANT, |
| FILED SMALL DENIED BIN "P"LEM |
| 5/22/18 SENT TO PROCESSING JLEAHY |
| 05/17/2018 FABRICE RESUB TO ADDRESS DENIED |
| COMMENTS JS |
| 5/7/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
| "P". CP |
| 5/7/18 - REVIEW COMPLETED.SENT TO |
| INCOMING/PROCESSING.TKL. |
| 4/30/18 MARK RESUB TO ADDRESS DENIED COMMENTS |
| SHOLDER |
| 3/21/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
| "P". CP |
| 3/21/18 - DENIED/SENT TO INCOMING. 4X PLAN REVIEW |
| FEE SHALL BE PAID ON NEXT RESUBMITTAL. TKL |
| 3/19/18 FABRICE RESUB TO ADDRESS DENIED COMMENTS |
| SL |
| 3/8/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
| "P". CP |
| 03/01/2018 FABRICE RESUB TO ADDRESS DENIED |
| COMMENTS JS |
| 1/24/18 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED UNDER SMALL DENIED |
| "P". CP |
| 1/24/18 SENT TO PROCESSING JLEAHY |