| Miscellaneous Information / Notes |
| 54,000 SF ADDITION TO DRY DEPOT |
| |
| |
| 11/28/18 PICKED UP CO RES |
| 11/09/2018 CERTIFICATE OF OCCUPANCY PRINTED AND |
| PLACED AT FRONT COUNTER, FILED UNDER "W" WITH COPY |
| SENT TO SCANNING. MM |
| 9/5/18 TCO EXTENDED 90 DAYS. SAK |
| 6/6/18 ISSUED TCO. SAK |
| 5/14/18 RECEIVED ORIGINAL TCO ROUTED TO STEVEN |
| KENNEDY & SCANNED TO THIS PERMIT SPALMER |
| 5/10/17 RECEIVED TCO REQUEST VIA EMAIL, ORIGINAL |
| FORTHCOMING, EXPECTED TO BE DELIVERED 5/14/18, SEE |
| ATTACHED. SAK |
| 12/15/17 BARRINGTON P/U PERMIT SPALMER |
| 12/4/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
| READY TO BE PICKED UP, FILED UNDER LARGE "W". CP |
| 11/29/17 PLUMB APPROVED RETURN TO C39/GPJ |
| 11/20/17 RE-SUB SUCCESSFUL, DATED 11/16/17 TO C39. |
| SAK |
| 11/16/17 PLANS CANNOT BE FOUND FOR ATTEMPTED |
| RE-SUBMITTAL. SAK |
| 10/27/17 ELEC PASS, EMAILED CONTRACTOR AND PLACED |
| ON TOP OF LARGE DENIED BIN. JP |
| 10/27/2017 - ZONING PASSED W PROVISO. SEPARATE |
| PERMIT REQUIRED FOR LANDSCAPE IMPROVEMENTS. |
| RETURNED TO C39. LL |
| 10/17/17 PLUMB DENIED RETURN TO C39/GPJ |
| 10/13/17 PASSED BY FIRE RETURNED TO C39.PML |
| 10/11/17 BARRY RESUB PER DENIED COMMENTS RES |
| 9/25/17 BARRY SIGNED OUT 1 SET OF PLANS FOR IMPACT |
| SPALMER |
| 9/25/17 PLAN REVIEW COMPLETE, PLANS IN LARGE |
| DENIED "TBD 1" AS THERE WAS NO ROOM IN W. LEM |
| 9/13/17 PLUMBING DENIED RETURN TO C40/GPJ |
| 8/24/17 - ZONING APPROVED WITH PROVISO. RETURNED |
| TO C40. LL |
| 8/15/17 PASSED BY FIRE WITH PROVISO COMMENTS, |
| RETURNED TO C40.PML |