| Miscellaneous Information / Notes |
| FOOTINGS & FOUNDATIONS FOR PROPOSED NEW ADDITION |
| TO EXISTING SCHOOL BLDG |
| **EXPANDED SCOPE TO INCLUDE STEEL STRUCTURE** |
| |
| |
| |
| 11/6/17 IMPACT FEES PAID, SCOPE EXPANDED TO |
| INCLUDE STEEL STRUCTURE UNDER REVISION 17100798 SH |
| 10/10/17 HEATH PICKED UP PERMIT RES |
| 9/26/17 EMAILED APPLICANT TO INFORM THAT PERMIT IS |
| READY FOR ISSUANCE PENDING PAYMENT OF FEES DUE, |
| UPDATE OF CONTRACTOR LICENSE IF APPLICABLE, AND |
| OWNER'S NOTARIZED SIGNATURE ON APPLICATION IF |
| APPLICABLE. 1 CONTRACTOR SET AND OUR FILE SET ARE |
| FILED IN LARGE PLANS UNDER "A"SH |
| 9/25/17 PASSED BY FIRE, FORWARDED TO BUILDING.PML |
| 9/20/17 2ND RESUB, NO FEE SH |
| 9/20/17 THRESHOLD INSPECTION PLAN AND SI AGREEMENT |
| OK W/PROVISO, ROUTED ORIGINALS TO RECORDS UNDER |
| PERMIT NUMBERS 17060234 & 17060807 SH |
| 9/20/17 PLANS IN BLDG DIV CONFERENCE ROOM SH |
| 8/30/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEED TO RESUBMIT, FILED ABOVE DENIED |
| CABINETS". CP |
| 8/28/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C02.PML |
| 8/25/17 - ZONING FAILED. RETURNED TO C2. LL |
| 8/24/17 PLUMB DENIED RETURN TO C02/GPJ |
| 8/23/17 ELEC DENIED, RETURN TO C02. JP |
| |
| 8/21/17 DERECK RESUB PER DENIED COMMENTS; TURNED |
| IN A COMPLETE NEW SET OF PLANS RES |
| 8/11/17 MODIFIED PLAN REVIEW COMMENT TO BE |
| CONSISTENT WITH FIRE REVIEW, CALLED D.WINNINGS AND |
| LEFT MESSAGE, SH |
| 7/20/17 PLAN REVIEW COMPLETE, CUSTOMER INFORMED |
| THEY NEEDS TO RESUBMIT, FILED UNDER LARGE DENIED |
| "A". CP |
| 7/11/17 MOVED TO ENG BOX. CP |
| 7/3/17 - ZONING FAILED. RETURNED TO C2. LL |
| 6/19/17 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C02.PML |
| 6/15/17 1 SET OF EARLY START REQUEST AND LETTER |
| REQUESTING REDUCED OCCUPANT LOAD ROUTED TO R.BROWN |
| DESK; 2 ADDITIONAL SETS IN APPLICATION PACKAGE SH |
| 6/14/17 PLUMB DENIED RETURN TO C02/GPJ |
| 6/14/17 ELEC PASSED-FOUNDATION ONLY. RETURN TO |
| C02. JP |
| |
| 6/9/17 APPLICANT BROUGHT IN THE PLANS ROUTED |
| THROUGH INCOMING GD |
| 6/6/14 APPLICATION IS IN SMALL DENIED A AS THE |
| APPLICANT HAS AGREED TO RETURN WITH THREE SETS OF |
| PLANS IN THE COMING DAYS. SAK |
| 6/6/17 REQUEST FOR EXPEDITE PLAN REVIEW ROUTED |
| THROUGH INCOMING GD |