| Miscellaneous Information / Notes |
| TENANT IMPROVEMENT INTERIOR FOR A DOG DAYCARE |
| /KENNEL AND GROOMING W/ RETAIL "CENTRAL BARK" |
| |
| |
| |
| 4/5/17 READY IN LARGE T/EMAILED CONTR/CC |
| 4/5/17 RESUB TO VPEREZ DESK. SAK |
| 3/7/17 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
| RESUBMIT, FILED UNDER LARGE DENIED "T". CP |
| 3/6/17 ROUTED TO AWOOTEN. CP |
| 2/28/17 FABRIZZIO RESUB TO ADDRESS DENIED COMMENTS |
| SHOLDER |
| 2/27/17 PLAN REVIEW COMPLETE, CUSTOMER NEEDS TO |
| RESUBMIT, FILED UNDER LARGE DENIED "T". CP |
| 2/21/17 ACCEPTED MID-CYCLE RE-SUB, BACK TO B31. |
| SAK |
| 2/16/17 ISSUED EARLY START AUTHORIZATION LETTER TO |
| RAMSES RODRIGUEZ VIA EMAIL. RB |
| 2/15/17 PLUMB APPROVED RETURN TO B31/GPJ |
| 1/30/17 APPLICATION DENIED, EMAILED APPLICANT, |
| FILED LARGE DENIED BIN "T"LEM |
| 1/19/17 PASSED BY FIRE, RETURNED TO C09.PML |
| 1/17/17 RESUB ADDRESSING DENIED COMMENTS NO FEES |
| GD |
| 1/17/17 CHANGE OF CONTRACTOR FORM SUBMITTED PRIOR |
| TO THE PERMIT BEING ISSUDED FROM MASTERS |
| CONTRACTORS INC TO TRI-R CONSTRUCTION COMPANY |
| PROCESSED GD |
| 1/12/17 PLUMB DENIED IN SMALL DENIED M CONT CUCT |
| /GPJ |
| 1/12/17 APPLICANT IS AUTHORIZED TO RE-SUMBIT FOR |
| THIRD REVIEW PRIOR TO THE COMPLETION OF THE SECOND |
| REVIEW AS PLUMBING ONLY IS OUTSTANDING AND BEHIND. |
| FEEL FREE TO COORDINATE WITH ME. SAK |
| 12/28/16 FAILED BY FIRE WITH COMMENTS, RETURNED TO |
| C09.PML |
| 12/20/16 RESUB ADDRESSING DENIED COMMENTS NO FEE |
| SPALMER |
| 12/15/16 RETURNED PLAN TO LARGE DENIED BIN 'M' SH |
| 12/14/16 RESUB CUSTOMER BROUGHT PLANS BACK FROM |
| IMPACT FEES GD |
| 12/14/2016 GARY SIGNED OUT 1 SET OF PLANS SHOLDER |
| 11/29/16 CORR, EMAILED APPLICANT, FILED DENIED |
| LARGE BIN 'M' SH |
| 11/3/16 REQUEST FOR EXPEDITE RECEIVED. GDORSAN |