| Miscellaneous Information / Notes |
| NEW CONSTRUCTION OF 6 MULTI-FAMILY UNITS (ROYAL |
| PALM PLACE BUILDING 3) |
| |
| 10/7/2020 PG RE-PRINTED C/O PER CRAIG'S REQUEST. |
| GAVE TO CRAIG FOR A CUSTOMER. ATTACHED IN C+ |
| |
| |
| 02-11-19 RECIVED FINAL CONSTRUCTION DOCS FROM |
| CONTRACTOR. |
| |
| 12/21/18 ISSUED TCO,SENT TO FILENET & ATTACHED. |
| SAK |
| |
| |
| **********EXPEDITED PLAN REVIEW |
| REQUESTED********** |
| |
| |
| |
| 12/11/17 VERIFIED SHEETS; ALLOWED APPLICANT TO |
| STAMP ONE B&W SET WITH PERMIT # STAMP (DUE TO COST |
| OF COLOR PLANS) SH |
| 8/10/17 DANNY P/U PERMIT SPALMER |
| 8/10/17 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| PAY FEES, DOWNLOAD PLANS & PICK UP PERMIT CARD. CP |
| 8/10/17 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 8/9/17 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 8/4/17 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 7/31/17 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 7/19/17 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 7/17/17 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 7/3/17 APPLICANT RESUBMITTED, INCOMING COMPLETE. |
| CP |
| 6/26/17 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 5/18/17 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 5/9/17 RESUB WAS GIVEN IN PAPER, HAD PARTIAL |
| PLANS, NOT ROUTED, APPLICANT NOTIFIED TO RESUBMIT |
| DIGITALLY. LEM |
| 5/8/17 RESUB ADDRESSING DENIED COMMENTS NO FEES GD |
| 11/21/16 RESUBMIT REMINDER SENT. LEM |
| 10/20/16 APPLICANT INVITED TO RESUBMIT. CP |
| 9/29/16 SENT THRESHOLD DOCS VIA EMAIL TO |
| [email protected] SH |
| 9/17/16 ADJUSTED VALUE PER ICC TABLES SH |
| 8/15/16 PLANS UPLOADED, FEES PAID, INCOMING |
| COMPLETE. CP |
| 8/9/16 APPLICANT PAID FEES, WAITING ON APPLICANT |
| TO UPLOAD PLANS. CP |
| 7/26/16 APPLICANT INVITED TO UPLOAD PLANS & PAY |
| FEES. CP |