| Miscellaneous Information / Notes |
| OKEECHOBEE COMMONS SITE ENTRY TOWER |
| |
| **ORIGINAL SIGNED & SEALED DOCUMENTS IN LIBRARY |
| WITH PERMIT APP** |
| |
| 11/07/2017 CERTIFICATE OF COMPLETION PRINTED AND |
| PLACED AT FRONT COUNTER, FILED UNDER "E" WITH COPY |
| SENT TO SCANNING. MM |
| |
| 12/14/16 PERMIT PICKED UP BY STEVE GD |
| 9/20/16 PLANS IN FILENET. LEM |
| 9/12/16 PLAN REVIEW COMPLETE, APPLICANT INVITED TO |
| DOWNLOAD PLANS, NEEDS TO PAY OUTSTANDING FEES, |
| NEEDS TO PICK UP PERMIT CARD. LEM |
| 9/9/16 WAITING ON DIGITAL SIGNATURE REVIEW BY |
| SKENNEDY. LEM |
| 9/2/16 PASSED "PROVISOS: |
| 1.) APPLICANT SHALL OBTAIN A ROW PERMIT FROM THE |
| PALM BEACH COUNTY DEPARTMENT OF ENGINEERING AND |
| PUBLIC WORKS FOR THE ACCESS POINT ON SKEES RD. |
| PRIOR TO FIRST INSPECTION. |
| 2.) ALL OTHER CONDITIONS OF APPROVAL IN RESOLUTION |
| NO. 322-15 REMAIN IN EFFECT." AV |
| |
| 8/25/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 8/18/16 APPLICANT RESUBMIT REMINDER SENT. CP |
| 7/19/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. LEM |
| 7/13/16 - ZONING FAILED. LL |
| 7/11/16 RESUBMIT RECEIVED, INCOMING COMPLETE. LEM |
| 6/24/16 PLAN REVIEW COMPLETE, APPLICANT NEEDS TO |
| RESUBMIT. CP |
| 6/22/16 - ZONING FAILED. LL |
| 5/18/16 FEES PAID, INCOMING COMPLETE. LEM |
| 5/18/16 PLANS UPLOADED, WAITING ON FEES. LEM |
| 5/13/16 APPLICANT INVITED TO UPLOAD PLANS AND PAY |
| FEES. LEM |