| Miscellaneous Information / Notes |
| REMODEL AND ADD ON GARAGE |
| |
| |
| |
| |
| |
| |
| 7/13/16 BRYAN P/U PERMIT SPALMER |
| 7/13/16 PLAN REVIEW COMPLETE, CUSTOMER INFORMED, |
| FILED UNDER LARGE "T". CP |
| 7/13/16 - ZONING PASSED WITH PROVISO. LANDSCAPE |
| PERMIT APPLICATION REQUIRED PRIOR TO THE ISSUANCE |
| OF PERMIT. RCARANCI SPOKE TO BRYAN OF TECKTONICA |
| AND WAS TOLD A PERMIT FOR LANDSCAPING WOULD BE |
| SUBMITTED TODAY. LL |
| 07/08/16 PLANS SENT TO ZONING SHELF FOR LINDA'S |
| REVIEW. JG. |
| 7/1/16 - PLANS ROUTED TO JG FOR BUILDING REVIEW; |
| LANDSCAPE STOP ADDED TO REVIEW EXISTING LANDSCAPE |
| PLAN. ROUTE TO ZONING LAST. LL |
| 6/29/16 RESUB ADDRESSING DENIED COMMENTS MS |
| |
| 6/20/16 PLUMB + GAS APPROVED SENT TO LARGE T |
| DENIED BIN EMAILED CONTRACTOR/GPJ |
| 06/17/16 PLANS SENT TO GEORGE JOHNSON FOR |
| PLUMBING/GAS REVIEW. JG. |
| |
| 6/13/16 - ZONING FAILED. RETURNED TO R27. LL |
| 5/31/16 RESUB SUBMITTED ADDRESSING DENIED |
| COMMENTS, NO FEE. LWL |
| 05/24/16 TALKED TO DAVID JONES TO GO OVER ENERGY |
| COMMENTS. JG. |
| 5/23/16 GAS DENIED IN LARGE T EMAIL CONT./ GPJ |
| 05/20/16 PLANS WERE REVISED. PLANS SENT TO GEORGE |
| FOR PLUMBING/GAS REVIEW. JG. |
| |
| 5/6/16 - ZONING FAILED. RETURNED TO R14. LL |
| 5/2/16 RESUB ADDRESSING COMMENTS ASM |
| 03/14/16 TALKED TO CONTRACTOR. PLANS IN BACK |
| DENIED LARGE PLANS FILES UNDER "T". JG. |
| 3/3/16 FAILED 1ST ELECTRICAL REVIEW AS NOTED. |
| RETURNED FILE TO BIN R31 FOR FURTHER REVIEWS. MA |
| 2/29/16 - ZONING FAILED. RETURNED TO R31. LL |
| 2/26/16 PLMB + GAS PASSED RETURN TO R31 /GPJ |